Microsoft Donnacona datacentre

Location
Donnacona, Portneuf, QC, Canada. See it on the map, in 3D
Stage
Under construction, as of April 2026 (Microsoft). Microsoft's own update says the datacentre building finished in November 2025 but substation and soundwall work was still expected to run through the second half of 2026, with no opening announced.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerMicrosoft
TypeHyperscale, self-builtMicrosoft
AmountNot found in the sources consulted
Sourced facts of the campus

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Substation capacitysubstation and sound walls to be completed in the second half of 2026Whole campusMicrosoft
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
MicrosoftOwnerMicrosoft
Domaco EncocorpGeneral contractorListed as the construction-site contact in Microsoft's update.Microsoft
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
February 12, 2024Construction of the first phase began.Microsoft
February 12, 2024Microsoft
November 2025The datacentre building structure was completed.Microsoft
November 2025Microsoft
2026 (planned)Substation and soundwall work expected to finish in the second half of 2026.Microsoft
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Microsoft is building a datacentre in Donnacona, Portneuf County, Quebec. Construction of the first building began in February 2024 and the building structure was completed in November 2025, but substation and soundwall work was expected to continue into the second half of 2026. No opening or energization date has been published.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.