Research record, fact-checked
Microsoft Donnacona datacentre
- Location
- Donnacona, Portneuf, QC, Canada. See it on the map, in 3D
- Stage
- Under construction, as of April 2026 (Microsoft). Microsoft's own update says the datacentre building finished in November 2025 but substation and soundwall work was still expected to run through the second half of 2026, with no opening announced.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Microsoft | |
| Type | Hyperscale, self-built | Microsoft |
| Amount | Not found in the sources consulted |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Substation capacity | substation and sound walls to be completed in the second half of 2026 | Whole campus | Microsoft |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Microsoft | Owner | Microsoft | |
| Domaco Encocorp | General contractor | Listed as the construction-site contact in Microsoft's update. | Microsoft |
Milestones
| Date | Milestone | Source |
|---|---|---|
| February 12, 2024 | Construction of the first phase began. | Microsoft |
| February 12, 2024 | Microsoft | |
| November 2025 | The datacentre building structure was completed. | Microsoft |
| November 2025 | Microsoft | |
| 2026 (planned) | Substation and soundwall work expected to finish in the second half of 2026. | Microsoft |
About the campus
Microsoft is building a datacentre in Donnacona, Portneuf County, Quebec. Construction of the first building began in February 2024 and the building structure was completed in November 2025, but substation and soundwall work was expected to continue into the second half of 2026. No opening or energization date has been published.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Donnacona datacentre construction update, Microsoft. Consulted 19 Nov 2026.
- Donnacona datacentre construction update (French), Microsoft. Consulted 20 Nov 2026.