Microsoft Lévis datacenter

Location
Levis, QC, Canada. Site address: 2441 avenue de la Rotonde, Lévis QC G6X 2M2. See it on the map, in 3D
Stage
Under construction, as of April 2026 (Microsoft). Microsoft's April 2026 update describes ground works as complete and civil works (retention basins, internal roads, paving, landscaping) continuing until autumn 2026; no building completion or opening is stated.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerMicrosoft
TypeHyperscale, self-builtMicrosoft
AmountNot found in the sources consulted
Sourced facts of the campus

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
MicrosoftOwnerMicrosoft
Pomerleau ConstructionGeneral contractorMicrosoft
PomerleauGeneral contractorfirst phaseMicrosoft
Hardroc Blasting, Inc.Site preparationfirst phaseMicrosoft
Hydro-QuebecEnergy partnerHydro-Québec
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
April 2024Construction of the first phase began.Microsoft
November 2024Microsoft
July 2025Microsoft
April 2026Intensive ground works complete; civil works continuing to autumn 2026.Microsoft
April 2026Microsoft
April 2026Microsoft
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Microsoft is building a datacentre in the Charny neighbourhood of Levis, Quebec. Construction of the first phase began in April 2024 with Pomerleau Construction as general contractor. By an April 2026 update, ground works were complete and civil works (retention basins, roads, paving, landscaping) were expected to continue until autumn 2026. This is a different site from the QScale Q01 campus also located in Levis.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.