Microsoft Lévis datacenter
- Location
- Levis, QC, Canada. Site address: 2441 avenue de la Rotonde, Lévis QC G6X 2M2. See it on the map, in 3D
- Stage
- Under construction, as of April 2026 (Microsoft). Microsoft's April 2026 update describes ground works as complete and civil works (retention basins, internal roads, paving, landscaping) continuing until autumn 2026; no building completion or opening is stated.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Microsoft | |
| Type | Hyperscale, self-built | Microsoft |
| Amount | Not found in the sources consulted |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Microsoft | Owner | Microsoft | |
| Pomerleau Construction | General contractor | Microsoft | |
| Pomerleau | General contractor | first phase | Microsoft |
| Hardroc Blasting, Inc. | Site preparation | first phase | Microsoft |
| Hydro-Quebec | Energy partner | Hydro-Québec |
Milestones
| Date | Milestone | Source |
|---|---|---|
| April 2024 | Construction of the first phase began. | Microsoft |
| November 2024 | Microsoft | |
| July 2025 | Microsoft | |
| April 2026 | Intensive ground works complete; civil works continuing to autumn 2026. | Microsoft |
| April 2026 | Microsoft | |
| April 2026 | Microsoft |
About the campus
Microsoft is building a datacentre in the Charny neighbourhood of Levis, Quebec. Construction of the first phase began in April 2024 with Pomerleau Construction as general contractor. By an April 2026 update, ground works were complete and civil works (retention basins, roads, paving, landscaping) were expected to continue until autumn 2026. This is a different site from the QScale Q01 campus also located in Levis.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Levis datacentre project updates, Microsoft. Consulted 19 Nov 2026.
- Projet de centre de donnees de Levis, mises a jour, Microsoft. Consulted 20 Nov 2026.
- Projet de centre de donnees de Levis, mises a jour, Microsoft. Consulted 20 Nov 2026.
- Info-projet, Raccordement du centre de données de Microsoft: optimisation du projet et information sur la solution retenue (octobre 2024), Hydro-Québec, 1 Oct 2024. Consulted 20 Nov 2026.
- Titulaires d'un permis d'utilisation pour des équipements pétroliers à risque élevé, région 12 Chaudière-Appalaches (mise à jour 2026-11-16), page 12, Régie du bâtiment du Québec, 16 Nov 2026. Consulted 20 Nov 2026.
- Ligne à 230 kV entre le poste de Lévis et le client MSX-Lévis, tracé retenu optimisé, carte 1 (octobre 2024), Hydro-Québec, 10 Oct 2024. Consulted 20 Nov 2026.
- Raccordement à 230 kV à Lévis, Hydro-Québec. Consulted 20 Nov 2026.