Research record, fact-checked
Microsoft Mount Pleasant, Phase 2
- Location
- Mount Pleasant, WI, United States. See it on the map, in 3D
- Stage
- Under construction, as of March 2026 (Microsoft). Microsoft's March 2026 update says Phase 2 work is ongoing, with foundations, steel erection and underground utilities, and Phase 2 scheduled for completion in early 2028.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Microsoft | |
| Type | Hyperscale, self-built | Microsoft |
| Amount | Not found in the sources consulted |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Cooling | More than 90 percent closed-loop liquid cooling, remainder outside-air cooling switching to water on the hottest days | Whole campus | Microsoft |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Microsoft | Owner | Microsoft | |
| Walsh Construction | General contractor | Microsoft | |
| Kiewit | General contractor | Named general contractor in Microsoft's October 2024 update announcing site preparation from September 16, 2024; the update does not tie it to a phase. | Microsoft |
| We Energies | Energy partner | Microsoft |
About the campus
Microsoft is building the second phase of its Mount Pleasant, Wisconsin campus: Walsh Construction began Phase 2 work on November 1, 2025, in the area along KR and H. Microsoft's community page states that two datacenters are under construction at Mount Pleasant, with more than 90 percent closed-loop liquid cooling across the facility.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Mount Pleasant datacenter project update, Microsoft. Consulted 19 Nov 2026.
- Mount Pleasant datacenter project update, Microsoft. Consulted 20 Nov 2026.
- Understanding Microsoft datacenters in Racine County, Microsoft. Consulted 19 Nov 2026.