Research record, fact-checked

Microsoft Mount Pleasant, Phase 2

Location
Mount Pleasant, WI, United States. See it on the map, in 3D
Stage
Under construction, as of March 2026 (Microsoft). Microsoft's March 2026 update says Phase 2 work is ongoing, with foundations, steel erection and underground utilities, and Phase 2 scheduled for completion in early 2028.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerMicrosoft
TypeHyperscale, self-builtMicrosoft
AmountNot found in the sources consulted
Sourced facts of the campus

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
CoolingMore than 90 percent closed-loop liquid cooling, remainder outside-air cooling switching to water on the hottest daysWhole campusMicrosoft
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
MicrosoftOwnerMicrosoft
Walsh ConstructionGeneral contractorMicrosoft
KiewitGeneral contractorNamed general contractor in Microsoft's October 2024 update announcing site preparation from September 16, 2024; the update does not tie it to a phase.Microsoft
We EnergiesEnergy partnerMicrosoft
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
November 1, 2025Phase 2 construction began.Microsoft
2028Phase 2 scheduled completionMicrosoft
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Microsoft is building the second phase of its Mount Pleasant, Wisconsin campus: Walsh Construction began Phase 2 work on November 1, 2025, in the area along KR and H. Microsoft's community page states that two datacenters are under construction at Mount Pleasant, with more than 90 percent closed-loop liquid cooling across the facility.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.