ODATA DC QR03, Querétaro
- Location
- Queretaro, Mexico. See it on the map, in 3D
- Stage
- Partly in service, partly under construction, as of February 2025 (ODATA / Aligned Data Centers). ODATA energized 200 MW of the planned 300 MW campus in February 2025 while the remaining buildings continue toward full capacity.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | ODATA | |
| Type | Leased hyperscale campuses | |
| Headline amount | US$3.3 billion (US dollars), as of February 2025 | ODATA / Aligned Data Centers |
| What it covers | Announced investment: Investment figure stated with the campus energization announcement. Not to be read as a construction cost. |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 300 MW, planned | IT capacity (power for the computing equipment) | Whole campus | February 2025 | ODATA / Aligned Data Centers |
| 200 MW, delivered | Capacity, its measure not stated by the source | Whole campus, Phase 1 | February 2025 | ODATA / Aligned Data Centers |
| 72 MW | IT capacity (power for the computing equipment) | One building | ODATA / Aligned Data Centers |
Investment and financing
An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$3.3 bn | Announced investment | Whole campus | February 2025 | ODATA / Aligned Data CentersInvestment figure stated with the campus energization announcement. |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Buildings, in all | 5 | Whole campus | ODATA / Aligned Data Centers |
| Floor area | nearly three million square feet | Whole campus | ODATA / Aligned Data Centers |
| Substation capacity | expansion of a 400 kV switching substation, 6.2 miles of transmission lines and two new substations | Whole campus | ODATA / Aligned Data Centers |
| Floor area of one building | 116,118 m2 | One phase | GAYA |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| ODATA | Owner | ODATA / Aligned Data Centers | |
| Ammper | Energy partner | ODATA / Aligned Data Centers | |
| GAYA | Trade contractor | mechanical, electrical and plumbing (MEP) engineering and installation; first data center of the campus; GAYA states it engineered the project and built its mechanical, electrical and plumbing infrastructure in 90 days: medium and low voltage electrical, chilled water, fire protection, security, access control and smoke detection. | GAYA |
General contractor: Not found in the sources consulted.
Milestones
| Date | Milestone | Source |
|---|---|---|
| February 2025 | ODATA energized the first 200 MW phase of its QR03 campus in Queretaro. | ODATA / Aligned Data Centers |
About the campus
DC QR03 is ODATA's data center campus in the PyME Industrial Park, Queretaro, Mexico, planned for 300 MW of IT capacity across five buildings. ODATA energized the first 200 MW phase in February 2025, as part of a stated $3.3 billion campus investment, while the remaining capacity continues toward full build out.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- ODATA Announces Energization of Mexico's Largest Data Center Campus, Solving Energy Scarcity for the Development of Data Centers in Queretaro, ODATA / Aligned Data Centers, 27 Feb 2025. Consulted 19 Nov 2026.
- ODATA Announces Energization of Mexico's Largest Data Center Campus, Solving Energy Scarcity for the Development of Data Centers in Queretaro, ODATA / Aligned Data Centers, 27 Feb 2025. Consulted 20 Nov 2026.
- Mision Critica en tiempo record: el compromiso de GAYA con ODATA, GAYA, 3 Sep 2026. Consulted 20 Nov 2026.
- Misión Crítica en tiempo récord: el compromiso de GAYA con ODATA, GAYA, 3 Sep 2026. Consulted 20 Nov 2026.