Research record, fact-checked

ODATA DC QR03, Querétaro

Location
Queretaro, Mexico. See it on the map, in 3D
Stage
Partly in service, partly under construction, as of February 2025 (ODATA / Aligned Data Centers). ODATA energized 200 MW of the planned 300 MW campus in February 2025 while the remaining buildings continue toward full capacity.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerODATA
TypeLeased hyperscale campuses
Headline amountUS$3.3 billion (US dollars), as of February 2025ODATA / Aligned Data Centers
What it coversAnnounced investment: Investment figure stated with the campus energization announcement. Not to be read as a construction cost.
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
300 MW, plannedIT capacity (power for the computing equipment)Whole campusFebruary 2025ODATA / Aligned Data Centers
200 MW, deliveredCapacity, its measure not stated by the sourceWhole campus, Phase 1February 2025ODATA / Aligned Data Centers
72 MWIT capacity (power for the computing equipment)One buildingODATA / Aligned Data Centers
Capacity figures, each with what it measures

Investment and financing

An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
US$3.3 bnAnnounced investmentWhole campusFebruary 2025ODATA / Aligned Data CentersInvestment figure stated with the campus energization announcement.
Amounts, each with its kind and scope

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Buildings, in all5Whole campusODATA / Aligned Data Centers
Floor areanearly three million square feetWhole campusODATA / Aligned Data Centers
Substation capacityexpansion of a 400 kV switching substation, 6.2 miles of transmission lines and two new substationsWhole campusODATA / Aligned Data Centers
Floor area of one building116,118 m2One phaseGAYA
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
ODATAOwnerODATA / Aligned Data Centers
AmmperEnergy partnerODATA / Aligned Data Centers
GAYATrade contractormechanical, electrical and plumbing (MEP) engineering and installation; first data center of the campus; GAYA states it engineered the project and built its mechanical, electrical and plumbing infrastructure in 90 days: medium and low voltage electrical, chilled water, fire protection, security, access control and smoke detection.GAYA
Companies named by the operator, the developer, a filing or a government, each with its role

General contractor: Not found in the sources consulted.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
February 2025ODATA energized the first 200 MW phase of its QR03 campus in Queretaro.ODATA / Aligned Data Centers
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

DC QR03 is ODATA's data center campus in the PyME Industrial Park, Queretaro, Mexico, planned for 300 MW of IT capacity across five buildings. ODATA energized the first 200 MW phase in February 2025, as part of a stated $3.3 billion campus investment, while the remaining capacity continues toward full build out.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.