PHX01-01

Location
Avondale, Maricopa County, AZ, United States. Site address: 3700 S. Avondale Blvd. See it on the map, in 3D
Stage
Under construction, as of November 2026 (Prime Data Centers). Prime's Phoenix page, read on 2026-11-20, lists PHX01-01 to PHX01-03 as under construction and leased, PHX01-04 under construction and available, PHX01-05 in development.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
DeveloperPrime Data Centers
TypeLeased hyperscale campuses
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
48 MWIT capacity (power for the computing equipment)One building, Building PHX01-01 of the Prime Phoenix Campus PHX01October 2025Prime Data Centers
48 MWIT capacity (power for the computing equipment)One building, Building PHX01-02 of the Prime Phoenix Campus PHX01November 2026Prime Data Centers
48 MWIT capacity (power for the computing equipment)One building, Building PHX01-03 of the Prime Phoenix Campus PHX01October 2025Prime Data Centers
48 MWIT capacity (power for the computing equipment)One building, Building PHX01-04 of the Prime Phoenix Campus PHX01October 2025Prime Data Centers
250 MWCapacity, its measure not stated by the sourceWhole campusPrime Data Centers
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Floor area of one building267,000 sq ftOne buildingPrime Data Centers
Site area66.5 acresWhole campusPrime Data Centers
Buildings, in all5Whole campusPrime Data Centers
Floor area1,300,000 sq ftWhole campusPrime Data Centers
CoolingClosed air loop and liquidWhole campusPrime Data Centers
Substation capacitynullWhole campusPrime Data Centers
Buildings under construction4Whole campusPrime Data Centers
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Prime Data CentersDeveloperPrime Data Centers
SRP (Salt River Project)Energy partnerPrime Data Centers
ARCO/MurrayGeneral contractorPhase 1: site development, private substation coordination and core and shell of the first three buildings (PHX01-01 to PHX01-03); ARCO/Murray's own release describes its scope on the campus.ARCO/Murray
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
May 21, 2026Prime breaks ground on the first three data centers of the five-building PHX01 campus in AvondalePrime Data Centers
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

PHX01-01 is a 48MW, 267,000 square foot hyperscale building at 3700 S. Avondale Blvd, part of Prime Data Centers' 66.5-acre Phoenix Campus PHX01, planned for five hyperscale data centers totaling 240MW and 1.3 million square feet. Prime's own technical data sheet lists the building's status as Construction, with on-site substation power from SRP and closed air loop and liquid cooling.

  • PHX01-01: Building PHX01-01 of the Prime Phoenix Campus PHX01
  • PHX01-02: Building PHX01-02 of the Prime Phoenix Campus PHX01
  • PHX01-03: Building PHX01-03 of the Prime Phoenix Campus PHX01
  • PHX01-04: Building PHX01-04 of the Prime Phoenix Campus PHX01

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.

Sources

See it on the map. How the map is made.