QTS Cedar Rapids
- Location
- Cedar Rapids, Linn County, IA, United States. Site address: 6200 76th Ave SW, Cedar Rapids, Iowa 52228 (CDR1 DC1, Unit 100; DC2 Unit 200; DC3 Unit 300). See it on the map, in 3D
- Stage
- Under construction, as of October 2025 (The Weitz Company). On October 22, 2025, QTS and its builders celebrated the topping out of the first of three buildings at the campus.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Developer | QTS | |
| Type | Colocation | Cedar Rapids Economic Development |
| Amount | Not found in the sources consulted |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Site area | 612 acres | Whole campus | QTS Data Centers |
| Buildings, in all | 7 | Whole campus | QTS Data Centers |
| Buildings under construction | 3 | One phase | The Weitz Company |
| Floor area of one building | 400,000 to 1.2 million sq ft | One building | The Weitz Company |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| QTS | Developer | Cedar Rapids Economic Development | |
| Alliant Energy | Energy partner | Cedar Rapids Economic Development | |
| The Weitz Company | General contractor | Joint venture with Layton Construction (Layton | Weitz), building one of the campus's data center buildings. | The Weitz Company |
| Layton Construction | General contractor | Joint venture with The Weitz Company (Layton | Weitz). | The Weitz Company |
Milestones
| Date | Milestone | Source |
|---|---|---|
| February 12, 2025 | City of Cedar Rapids, Alliant Energy and QTS announce the project | Cedar Rapids Economic Development |
| October 22, 2025 | Topping out of the first of three campus buildings | The Weitz Company |
| 2026 | First construction phase anticipated complete (second phase anticipated 2027) | The Weitz Company |
About the campus
QTS is building a campus planned for seven data center buildings on 612 acres in the Big Cedar Industrial Center, Cedar Rapids, Iowa. On October 22, 2025, QTS, Layton Construction and The Weitz Company celebrated the topping out of the first of three buildings, with the first construction phase anticipated for completion in 2026 and the second in 2027. Weitz's project page gives the delivery method as a Layton | Weitz joint venture.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Data Centers, Cedar Rapids Economic Development. Consulted 19 Nov 2026.
- Cedar Rapids, QTS Data Centers. Consulted 19 Nov 2026.
- Cedar Rapids Data Center Campus, QTS Data Centers. Consulted 20 Nov 2026.
- QTS Data Center Campus (project page), The Weitz Company. Consulted 20 Nov 2026.
- QTS Celebrates Cedar Rapids Data Center Campus Topping Out Milestone, The Weitz Company, 22 Oct 2025. Consulted 20 Nov 2026.
- Parcels (FeatureServer layer 1), query by owner QTS CEDAR RAPIDS, City of Cedar Rapids GIS. Consulted 20 Nov 2026.