Research record, fact-checked
QTS Eagle Mountain
- Location
- Eagle Mountain, Utah County, UT, United States. See it on the map, in 3D
- Stage
- Under construction, as of November 19, 2026 (QTS Data Centers). QTS's own page states construction of the first three buildings is currently under way.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Developer | QTS | |
| Type | Colocation | QTS Data Centers |
| Headline amount | US$6 billion (US dollars), as of November 2026 | QTS Data Centers |
| What it covers | Announced investment: Covers the initial phase (buildings 1 through 5) per QTS's own page. Not to be read as a construction cost. |
Investment and financing
An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$6 bn | Announced investment | Whole campus | November 2026 | QTS Data CentersCovers the initial phase (buildings 1 through 5) per QTS's own page. |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Site area | About 193 acres | Whole campus | QTS Data Centers |
| Floor area of one building | 592,000 sq ft | One building | QTS Data Centers |
| Buildings under construction | 3 | Whole campus | QTS Data Centers |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| QTS | Developer | QTS Data Centers | |
| Layton Construction | General contractor | Layton's own news page reports topping out the QTS data center in Eagle Mountain (SLC1) | Layton Construction |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 2026 (planned) | Buildings 1, 2 and 3 expected complete by the end of the year | QTS Data Centers |
About the campus
QTS is building a data centre campus of approximately 193 acres in Eagle Mountain City, Utah County, Utah, representing a $6 billion investment. QTS's own page states construction of Buildings 1, 2 and 3 is currently under way and expected to be completed by the end of 2026, with individual buildings around 579,000 to 592,000 square feet and Buildings 4 and 5 to follow in later years.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Eagle Mountain, QTS Data Centers. Consulted 19 Nov 2026.
- Layton tops out massive data center in Eagle Mountain., Layton Construction. Consulted 20 Nov 2026.