Related Digital Cheyenne Campus

Location
Cheyenne, WY, United States. See it on the map, in 3D
Stage
Under construction, as of June 2026 (Related Digital). Related Digital's own news post of June 14 says work on the first phase is nearing completion, with over 400 construction workers on site.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
DeveloperRelated Digital
TypeLeased hyperscale campusesRelated Digital
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
88 MWIT capacity (power for the computing equipment)One buildingRelated Digital
Up to 420 MWCapacity, its measure not stated by the sourceWhole campusRelated Digital
Up to 302 MWCapacity, its measure not stated by the sourceWhole campusRelated Companies
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Site area115 acresWhole campusRelated Digital
Floor area of one building184,000 sq ftOne phaseRelated Digital
Buildings under construction1One phaseRelated Digital
Floor area of one building184,000 sq ftOne buildingRelated Companies
Site area36 acresOne phaseRelated Companies
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Related DigitalDeveloperRelated Digital
CoreWeaveTenantRelated Digital
Black Hills EnergyEnergy partnerRelated Digital
ClaycoGeneral contractorPhase I (first 184,000 sq ft building); Construction manager for the first phase.Related Companies
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
October 7, 2025Related Companies
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Related Digital is developing a 115-acre data center campus in the Cheyenne Business Parkway, Cheyenne, Wyoming, with up to 302 MW of critical IT capacity in its October 2025 announcement. The first building, 184,000 square feet on 36 acres for CoreWeave, broke ground on October 7, 2025 with Clayco as construction manager, and Related Digital said in June that work on it was nearing completion.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.