Related Digital Cheyenne Campus
- Location
- Cheyenne, WY, United States. See it on the map, in 3D
- Stage
- Under construction, as of June 2026 (Related Digital). Related Digital's own news post of June 14 says work on the first phase is nearing completion, with over 400 construction workers on site.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Developer | Related Digital | |
| Type | Leased hyperscale campuses | Related Digital |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 88 MW | IT capacity (power for the computing equipment) | One building | Related Digital | |
| Up to 420 MW | Capacity, its measure not stated by the source | Whole campus | Related Digital | |
| Up to 302 MW | Capacity, its measure not stated by the source | Whole campus | Related Companies |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Site area | 115 acres | Whole campus | Related Digital |
| Floor area of one building | 184,000 sq ft | One phase | Related Digital |
| Buildings under construction | 1 | One phase | Related Digital |
| Floor area of one building | 184,000 sq ft | One building | Related Companies |
| Site area | 36 acres | One phase | Related Companies |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Related Digital | Developer | Related Digital | |
| CoreWeave | Tenant | Related Digital | |
| Black Hills Energy | Energy partner | Related Digital | |
| Clayco | General contractor | Phase I (first 184,000 sq ft building); Construction manager for the first phase. | Related Companies |
Milestones
| Date | Milestone | Source |
|---|---|---|
| October 7, 2025 | Related Companies |
About the campus
Related Digital is developing a 115-acre data center campus in the Cheyenne Business Parkway, Cheyenne, Wyoming, with up to 302 MW of critical IT capacity in its October 2025 announcement. The first building, 184,000 square feet on 36 acres for CoreWeave, broke ground on October 7, 2025 with Clayco as construction manager, and Related Digital said in June that work on it was nearing completion.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Vertically integrated data center development, Related Digital. Consulted 19 Nov 2026.
- Vertically integrated data center development (Wyoming), Related Digital. Consulted 20 Nov 2026.
- Related Digital breaks ground on 302 MW data center campus in Cheyenne, Wyoming, Related Companies, 7 Oct 2025. Consulted 20 Nov 2026.
- Inside the $1.2 billion data center campus being built in Cheyenne, Related Digital. Consulted 20 Nov 2026.
- Assessor Parcels, CountyBaseMapFeatures layer 2 (tax year 2024), Cheyenne and Laramie County GIS Cooperative (Laramie County Assessor data), 30 May 2024. Consulted 20 Nov 2026.
- Data_Centers (Data Centers in Urban Cheyenne Area), feature layer, Cheyenne and Laramie County GIS Cooperative, 1 May 2026. Consulted 20 Nov 2026.