Research record, fact-checked

Stream San Antonio III (SATB1)

Location
San Antonio, Bexar County, TX, United States. Site address: 11203 Military Drive W, San Antonio, Texas 78251. See it on the map, in 3D
Stage
Opened, as of April 2026 (Stream Data Centers). Stream's April 2026 campus spec sheet says SATB1 has been commissioned; the other buildings are scheduled for occupancy between 2028 and 2031.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
DeveloperStream Data Centers
TypeLeased hyperscale campusesStream Data Centers
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
334 MVACapacity, its measure not stated by the sourceWhole campusNovember 2026Stream Data Centers
200 MW, plannedCapacity, its measure not stated by the sourceWhole campus, Full build (up to five buildings)November 2026Stream Data Centers
40 MWCapacity, its measure not stated by the sourceOne buildingTexas Department of Licensing and Regulation
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Floor area of one building300,000 sq ftOne buildingStream Data Centers
Floor area1,500,000 sq ftWhole campusStream Data Centers
Buildings, in allUp to fiveWhole campusStream Data Centers
Stories2One buildingStream Data Centers
Floor area1,430,490 sq ftWhole campusStream Data Centers
Site area135 acresWhole campusStream Data Centers
CoolingHigh-efficiency air-cooled chillers with water-side economization; zero water use cooling systemsWhole campusStream Data Centers
Substation capacity334 MWWhole campusStream Data Centers
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Stream Data CentersDeveloperStream Data Centers
CorganDesignSATB1; Design firm of record for SATB1 and its data hall fit-outsTexas Department of Licensing and Regulation
SDC SA III LPOwnerTexas Department of Licensing and Regulation
CPS EnergyEnergy partnerStream Data Centers
DPR ConstructionGeneral contractorSATB1 (SAT03 Building No. 1); Primary contact on the City of San Antonio new building, foundation and sitework permits for SAT03 Building No. 1; DPR describes the two-story, approximately 300,000 sq ft San Antonio data center on a five-building campus as DPR-led.City of San Antonio, Development Services Department (Open Data)
DPR ConstructionSite preparationPhased site work, grading and utilities; Primary contact on the phased sitework permit for grading and utilities.City of San Antonio, Development Services Department (Open Data)
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
September 27, 2023Texas Department of Licensing and Regulation
November 2, 2023Phased sitework permit (grading and utilities) issuedCity of San Antonio, Development Services Department (Open Data)
February 15, 2024New building permit issued for SAT03 Building No. 1City of San Antonio, Development Services Department (Open Data)
undefined 2028Stream Data Centers
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Stream Data Centers' third San Antonio campus, SATB, is a 135-acre site at 11203 W Military Drive planned for up to five two-story buildings, about 1.43 million square feet zoned and 200 MW at full build, with an on-site 334 MW CPS Energy substation. Its first building, SATB1, a 40 MW, 300,000 square foot data center designed by Corgan, has been commissioned and is fully leased, according to Stream's April 2026 spec sheet; the next buildings are scheduled for occupancy between 2028 and 2031.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.