Research record, fact-checked

T5 Chicago III, Northlake

Location
Northlake, IL, United States. Site address: 11650 W. Grand Ave., Northlake, Illinois 60164. See it on the map, in 3D
Stage
Under construction, as of September 2024 (Corgan). T5 broke ground on the Northlake building in September 2024, with Clune Construction as general contractor and completion expected in 2027.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerT5 Data Centers
TypeLeased hyperscale campuses
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
36 MWIT capacity (power for the computing equipment)One buildingOctober 2023T5 Data Centers
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Floor area of one building250,000 sq ftOne buildingClune Construction
Stories3One buildingCorgan
Buildings, in all1Whole campusCorgan
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
T5 Data CentersOwnerT5 Data Centers
Clune ConstructionGeneral contractorClune Construction
CorganDesignarchitectCorgan
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
October 3, 2023T5 announces acquisition of its third Chicago-market location, Chicago IIIT5 Data Centers
September 2024GroundbreakingCorgan
2027Expected completionCorgan
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

T5 Data Centers is building Chicago III, a three-story, 250,000-square-foot data center at 11650 W. Grand Ave. in Northlake, Illinois, its third in the Chicago area. T5 broke ground in September 2024 with Clune Construction as general contractor and Corgan as architect, and expects completion in 2027. T5's October 2023 acquisition announcement gave the site 36 MW of IT capacity.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.