Research record, fact-checked

Lake Mariner CB-4

Location
Barker, NY, United States. Site address: 7725 Lake Road, Barker, NY 14012. See it on the map, in 3D
Stage
Partly in service, partly under construction, as of November 2026 (TeraWulf Inc.). TeraWulf's Q3 2026 investor presentation lists five buildings operational at Lake Mariner and CB-4 and CB-5 under construction.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerTeraWulf
TypeAI and HPC campusesTeraWulf Inc.
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
168 MW, plannedIT capacity (power for the computing equipment)One building, Building CB-4 of the Lake Mariner campus2026TeraWulf Inc.
168 MW, plannedIT capacity (power for the computing equipment)One building, Building CB-5 of the Lake Mariner campus2026TeraWulf Inc.
168 MWIT capacity (power for the computing equipment)One building, CB-5TeraWulf Inc.
102 MWIT capacity (power for the computing equipment)Whole campus, operational buildingsTeraWulf Inc.
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Buildings delivered5Whole campusTeraWulf Inc.
Buildings under construction2Whole campusTeraWulf Inc.
Site areaAbout 79 acresWhole campusTeraWulf Inc.
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
FluidstackTenantNamed as a lease tenant of the Lake Mariner campus.TeraWulf Inc.
TeraWulfOwnerthrough its subsidiaries La Lupa Data LLC and Akela Data LLCTeraWulf Inc.
Core42TenantTeraWulf Inc.
GoogleFinancingbackstop of the leasesTeraWulf Inc.
New York Power AuthorityEnergy partnerTeraWulf Inc.
Wendel Construction, Inc.General contractorOriginal Lake Mariner Facility (bitcoin mining buildings, 2021 to 2022); Builder of the first buildings under a 2021 subcontract to TeraWulf's subsidiary Beowulf E&D; not named for CB-4 or CB-5.TeraWulf Inc.
Beowulf Electricity & Data LLC (Beowulf E&D)General contractorTeraWulf's own subsidiary, contractor on the original facility and in charge of development and construction functions.TeraWulf Inc.
Somerset Operating Company, LLClandownerTeraWulf Inc.
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
2026CB-3 is listed as operational and generating lease revenue.TeraWulf Inc.
undefined 12, 2026TeraWulf Inc.
undefined 2027TeraWulf Inc.
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Lake Mariner CB-4 is a building under construction at TeraWulf's Barker, New York campus, with 168 MW of IT capacity being delivered in phases during the fourth quarter under an amended lease schedule, per TeraWulf's own investor materials. The campus leases capacity to AI and HPC tenants including Fluidstack and Core42.

  • Lake Mariner CB-4: Building CB-4 of the Lake Mariner campus
  • Lake Mariner CB-5: Building CB-5 of the Lake Mariner campus
  • Lake Mariner CB-3: Building CB-3 of the Lake Mariner campus

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.

Sources

See it on the map. How the map is made.