Vantage Frontier, Shackelford County

Location
Shackelford County, TX, United States. Site address: 246 PR 1604, Abilene, TX 79601 (Shackelford County). See it on the map, in 3D
Stage
Under construction, as of August 2025 (Vantage Data Centers). Vantage's own announcement states construction has already begun
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
DeveloperVantage Data Centers
TypeLeased hyperscale campuses
Headline amountMore than US$25 billion (US dollars), as of August 2025Vantage Data Centers
What it coversAnnounced investment, lower bound: Stated as the investment for the whole campus. Not to be read as a construction cost.
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
1,400 MW, plannedCapacity, its measure not stated by the sourceWhole campusAugust 2025Vantage Data Centers
Capacity figures, each with what it measures

Investment and financing

An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
More than US$25 bnAnnounced investmentWhole campusAugust 2025Vantage Data CentersStated as the investment for the whole campus
Amounts, each with its kind and scope

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Buildings, in all10Whole campusVantage Data Centers
Floor area3,700,000 sq ftWhole campusVantage Data Centers
Site area1,200 acresWhole campusVantage Data Centers
Coolingliquid cooling to support next generation GPU loads; closed-loop chiller systemWhole campusVantage Data Centers
Floor area of one building344,796 sq ftOne buildingTexas Department of Licensing and Regulation
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Vantage Data CentersDeveloperVantage Data Centers
Vantage Data Centers TX301, LLCOwnerTexas Department of Licensing and Regulation
Companies named by the operator, the developer, a filing or a government, each with its role

General contractor: Not found in the sources consulted.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
August 2025Vantage states construction on the campus has already begunVantage Data Centers
June 29, 2026Texas Department of Licensing and Regulation
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Frontier is a Vantage Data Centers campus in Shackelford County, Texas, planned for 10 data centers totaling 3.7 million square feet on 1,200 acres, with 1.4GW of capacity. Vantage states construction had already begun as of its August 2025 announcement, with the first building scheduled for delivery in the second half of 2026, and describes an investment of over $25 billion.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.