Borrow Excavation unit price, Alabama
Low bidders on ALDOT contracts carried a median of $29.93 per CY for item 210D000, borrow excavation, over the 24 months to 28 AUG 2026, across 23 low bids. Half of all 77 bids fell between $26.00 and $50.01.
- Owner
- Alabama DOT
- Item
- 210D000
- Unit
- CY
- Latest letting
- 31 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 8 | 8 | $42.50 | 32 | $27.86 |
| 2023 | 9 | 9 | $28.71 | 28 | $27.51 |
| 2024 | 12 | 11 | $32.25 | 37 | $28.83 |
| 2025 | 13 | 13 | $27.00 | 44 | $39.07 |
| 2026 | 4 | 4 | $30.98 | 15 | $75.44 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| 0301 | 6 | $40.72 | 27 | $50.00 |
| 0201 | 3 | $24.50 | 10 | $26.59 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 10 to 585 | 5 | $50.00 |
| 995 to 6,473 | 6 | $27.21 |
| 7,929 to 16,418 | 6 | $26.50 |
| 18,292 to 116,298 | 6 | $24.83 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 31 JUL 2026 | 20260731001 | 0301 | 368 | $30.00 | $82.59 | 6 | IKAROS, LLC | ALDOT |
| 29 MAY 2026 | 20260529023 | 0301 | 585 | $75.44 | $98.93 | 4 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 30 JAN 2026 | 20260130025 | 0102 | 12,535 | $23.00 | $27.50 | 4 | ROGERS GROUP, INC. | ALDOT |
| 30 JAN 2026 | 20260130031 | 0401 | 7,929 | $31.95 | $31.95 | 1 | GARY INGRAM GRADING & PAVING, INC. | ALDOT |
| 05 DEC 2025 | 20251205002 | 0201 | 21,149 | $23.66 | $23.66 | 3 | MILLER & MILLER, INC. | ALDOT |
| 05 DEC 2025 | 20251205021 | 0103 | 1,224 | $24.11 | $34.00 | 3 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 26 SEP 2025 | 20250926033 | 0502 | 1,183 | $29.93 | $42.50 | 4 | GFC CONSTRUCTION, INC. | ALDOT |
| 25 JUL 2025 | 20250725001 | 0301 | 42,592 | $42.00 | $45.30 | 7 | GILLESPIE CONSTRUCTION, LLC | ALDOT |
| 25 JUL 2025 | 20250725008 | 0103 | 23,913 | $26.00 | $27.93 | 4 | ROGERS GROUP, INC. | ALDOT |
| 25 JUL 2025 | 20250725012 | 0201 | 367 | $45.00 | $47.50 | 4 | ROGERS GROUP, INC. | ALDOT |
| 30 MAY 2025 | 20250530001 | 0305 | 1,596 | $23.03 | $21.91 | 4 | CHILTON CONTRACTORS, INC. | ALDOT |
| 28 MAR 2025 | 20250328001 | 0301 | 16,418 | $27.00 | $40.65 | 4 | MURPHREE BRIDGE CORPORATION | ALDOT |
| 28 MAR 2025 | 20250328004 | 0404 | 2,136 | $90.00 | $90.00 | 1 | VULCAN MATERIALS ASPHALT AND CONSTRUCTION, | ALDOT |
| 28 FEB 2025 | 20250228001 | 0202 | 8,506 | $26.00 | $26.00 | 3 | MILLER & MILLER, INC. | ALDOT |
| 28 FEB 2025 | 20250228044 | 0105 | 10 | $687.08 | $295.00 | 3 | TEMPLE J ELECTRIC, LLC | ALDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.
How these prices were read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.