Machine Grading Shoulders unit price, Alabama

Low bidders on ALDOT contracts carried a median of $67.62 per STA for item 212A000, machine grading shoulders, over the 24 months to 28 AUG 2026, across 64 low bids. Half of all 150 bids fell between $48.19 and $243.54.

Owner
Alabama DOT
Item
212A000
Unit
STA
Latest letting
28 AUG 2026
$67.62Low bidder's median, per STA
$69.78Median of all bids, per STA
64Contracts in the window

By year of letting

Machine Grading Shoulders, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222121$74.0045$80.05
20232222$53.7049$55.00
20242525$55.5761$60.00
20252424$67.6253$65.00
20262929$98.1069$78.00
Machine Grading Shoulders, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Machine Grading Shoulders, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
05027$442.8018$496.40
08048$42.5117$49.12
09026$175.0015$101.84
07045$55.0015$62.96
07025$54.8914$60.47
10084$776.859$756.96
08023$30.306$31.23
06043$55.005$50.00
05063$775.003$775.00
Machine Grading Shoulders, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Machine Grading Shoulders, ALDOT: low bidder's median by quantity band
Quantity (STA)Low bidsLow-bid median
2 to 2316$583.92
23 to 13416$126.08
186 to 80016$45.61
801 to 1,66916$47.50
Machine Grading Shoulders, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Machine Grading Shoulders
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 202620260828004050240$646.15$598.086IVS HYDRO, INC.ALDOT
28 AUG 202620260828021100882$796.73$517.013DUNN CONSTRUCTION COMPANY, INC.ALDOT
31 JUL 202620260731005050639$213.51$213.511S. T. BUNN CONSTRUCTION COMPANY, INC.ALDOT
26 JUN 2026202606260050502128$120.34$147.392APAC-ALABAMA, INC.ALDOT
26 JUN 2026202606260220803801$32.20$38.752WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
26 JUN 202620260626027060136$75.00$77.003ASPHALT CONTRACTORS, INC.ALDOT
29 MAY 2026202605290180804413$26.47$38.612APAC-ALABAMA, INC.ALDOT
24 APR 202620260424026090210$421.97$244.402APAC-ALABAMA, INC.ALDOT
24 APR 2026202604240280804871$20.00$41.902WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 20262026032701009026$553.32$467.472WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 2026202603270340704186$55.00$55.003SOUTHEAST CONSTRUCTION COMPANY, LLCALDOT
27 MAR 2026202603270370505660$34.70$32.122APAC-ALABAMA, INC.ALDOT
27 MAR 2026202603270380704659$62.96$60.003WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 202620260327039100814$756.96$756.961WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 2026202603270400706669$46.82$47.552APAC-ALABAMA, INC.ALDOT
Latest ALDOT contracts carrying Machine Grading Shoulders

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.