Roadbed Processing unit price, Alabama

Low bidders on ALDOT contracts carried a median of $739.83 per RBST for item 230A000, roadbed processing, over the 24 months to 28 AUG 2026, across 38 low bids. Half of all 149 bids fell between $640.03 and $1,379.86.

Owner
Alabama DOT
Item
230A000
Unit
RBST
Latest letting
28 AUG 2026
$739.83Low bidder's median, per RBST
$965.00Median of all bids, per RBST
38Contracts in the window

By year of letting

Roadbed Processing, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222424$876.1675$954.52
20231717$671.4147$765.55
20242323$634.4986$881.27
20252121$779.6581$1,000.00
202677$700.0030$964.42
Roadbed Processing, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Roadbed Processing, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
09025$357.5825$605.06
03015$1,039.9823$1,439.75
09016$958.4922$715.50
07044$718.0513$1,146.00
07014$943.1111$1,168.00
07023$1,379.8610$867.50
Roadbed Processing, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Roadbed Processing, ALDOT: low bidder's median by quantity band
Quantity (RBST)Low bidsLow-bid median
4 to 139$700.00
13 to 2510$857.33
27 to 429$963.84
45 to 18610$658.32
Roadbed Processing, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Roadbed Processing
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 202620260828011040232$700.00$765.054VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
31 JUL 20262026073102509029$250.00$737.736ARRINGTON CURB & EXCAVATION, INC.ALDOT
26 JUN 202620260626035090228$963.84$775.244WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 2026202605290010603186$611.18$611.183APAC-ALABAMA, INC.ALDOT
29 MAY 202620260529040070412$1,750.00$1,484.543APAC-ALABAMA, INC.ALDOT
24 APR 202620260424001070412$1,015.00$1,123.004F&W CONSTRUCTION COMPANY, INC.ALDOT
30 JAN 202620260130001010549$510.00$982.506ROGERS GROUP, INC.ALDOT
05 DEC 202520251205002020121$845.07$1,160.123MILLER & MILLER, INC.ALDOT
05 DEC 202520251205003090133$972.99$978.144MCINNIS CONSTRUCTION, LLCALDOT
05 DEC 202520251205008020129$680.81$1,017.215GRAYSON CARTER & SON CONTRACTING, INC.ALDOT
05 DEC 202520251205015070228$1,411.73$1,130.874WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
05 DEC 202520251205029070125$869.59$1,750.352APAC-ALABAMA, INC.ALDOT
05 DEC 202520251205062070114$1,016.62$1,326.954APAC-ALABAMA, INC.ALDOT
07 NOV 202520251107057080442$275.00$483.937PINE CITY CONTRACTING, LLCALDOT
26 SEP 202520250926027090145$1,224.53$926.443WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
Latest ALDOT contracts carrying Roadbed Processing

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way