Roadbed Processing unit price, Alabama
Low bidders on ALDOT contracts carried a median of $739.83 per RBST for item 230A000, roadbed processing, over the 24 months to 28 AUG 2026, across 38 low bids. Half of all 149 bids fell between $640.03 and $1,379.86.
- Owner
- Alabama DOT
- Item
- 230A000
- Unit
- RBST
- Latest letting
- 28 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 24 | 24 | $876.16 | 75 | $954.52 |
| 2023 | 17 | 17 | $671.41 | 47 | $765.55 |
| 2024 | 23 | 23 | $634.49 | 86 | $881.27 |
| 2025 | 21 | 21 | $779.65 | 81 | $1,000.00 |
| 2026 | 7 | 7 | $700.00 | 30 | $964.42 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| 0902 | 5 | $357.58 | 25 | $605.06 |
| 0301 | 5 | $1,039.98 | 23 | $1,439.75 |
| 0901 | 6 | $958.49 | 22 | $715.50 |
| 0704 | 4 | $718.05 | 13 | $1,146.00 |
| 0701 | 4 | $943.11 | 11 | $1,168.00 |
| 0702 | 3 | $1,379.86 | 10 | $867.50 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (RBST) | Low bids | Low-bid median |
|---|---|---|
| 4 to 13 | 9 | $700.00 |
| 13 to 25 | 10 | $857.33 |
| 27 to 42 | 9 | $963.84 |
| 45 to 186 | 10 | $658.32 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 AUG 2026 | 20260828011 | 0402 | 32 | $700.00 | $765.05 | 4 | VULCAN MATERIALS ASPHALT AND CONSTRUCTION, | ALDOT |
| 31 JUL 2026 | 20260731025 | 0902 | 9 | $250.00 | $737.73 | 6 | ARRINGTON CURB & EXCAVATION, INC. | ALDOT |
| 26 JUN 2026 | 20260626035 | 0902 | 28 | $963.84 | $775.24 | 4 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 29 MAY 2026 | 20260529001 | 0603 | 186 | $611.18 | $611.18 | 3 | APAC-ALABAMA, INC. | ALDOT |
| 29 MAY 2026 | 20260529040 | 0704 | 12 | $1,750.00 | $1,484.54 | 3 | APAC-ALABAMA, INC. | ALDOT |
| 24 APR 2026 | 20260424001 | 0704 | 12 | $1,015.00 | $1,123.00 | 4 | F&W CONSTRUCTION COMPANY, INC. | ALDOT |
| 30 JAN 2026 | 20260130001 | 0105 | 49 | $510.00 | $982.50 | 6 | ROGERS GROUP, INC. | ALDOT |
| 05 DEC 2025 | 20251205002 | 0201 | 21 | $845.07 | $1,160.12 | 3 | MILLER & MILLER, INC. | ALDOT |
| 05 DEC 2025 | 20251205003 | 0901 | 33 | $972.99 | $978.14 | 4 | MCINNIS CONSTRUCTION, LLC | ALDOT |
| 05 DEC 2025 | 20251205008 | 0201 | 29 | $680.81 | $1,017.21 | 5 | GRAYSON CARTER & SON CONTRACTING, INC. | ALDOT |
| 05 DEC 2025 | 20251205015 | 0702 | 28 | $1,411.73 | $1,130.87 | 4 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 05 DEC 2025 | 20251205029 | 0701 | 25 | $869.59 | $1,750.35 | 2 | APAC-ALABAMA, INC. | ALDOT |
| 05 DEC 2025 | 20251205062 | 0701 | 14 | $1,016.62 | $1,326.95 | 4 | APAC-ALABAMA, INC. | ALDOT |
| 07 NOV 2025 | 20251107057 | 0804 | 42 | $275.00 | $483.93 | 7 | PINE CITY CONTRACTING, LLC | ALDOT |
| 26 SEP 2025 | 20250926027 | 0901 | 45 | $1,224.53 | $926.44 | 3 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.
How these prices were read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way