Structure Excavation unit price, Alabama

Low bidders on ALDOT contracts carried a median of $23.00 per CY for item 214A000, structure excavation, over the 24 months to 28 AUG 2026, across 95 low bids. Half of all 354 bids fell between $16.56 and $53.14.

Owner
Alabama DOT
Item
214A000
Unit
CY
Latest letting
28 AUG 2026
$23.00Low bidder's median, per CY
$28.16Median of all bids, per CY
96Contracts in the window

By year of letting

Structure Excavation, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20223634$21.77101$22.50
20234747$25.00133$26.56
20244443$23.00165$24.49
20254746$21.69165$26.98
20262626$23.94105$28.95
Structure Excavation, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Structure Excavation, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
030112$50.0048$52.50
05027$16.5928$25.38
09025$17.2126$21.19
09017$38.7924$22.00
01055$30.4222$35.00
08043$50.0016$50.00
02014$18.6416$23.49
06014$37.5715$45.23
07024$26.9815$24.63
06065$17.2510$17.49
01033$15.2010$14.41
07013$7.579$20.00
Structure Excavation, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Structure Excavation, ALDOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
1 to 7523$38.79
88 to 25424$32.45
300 to 1,39024$17.95
1,427 to 15,81024$19.26
Structure Excavation, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Structure Excavation
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 2026202608280110402171$30.00$24.554VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
28 AUG 2026202608280300202135$8.80$45.278ROGERS GROUP, INC.ALDOT
31 JUL 2026202607310010301932$30.00$27.846IKAROS, LLCALDOT
31 JUL 202620260731017040215,810$22.87$18.004ALABAMA GRADING & EXCAVATION, LLC.ALDOT
31 JUL 2026202607310220105762$13.16$35.005LAMBERT CONTRACTING, LLCALDOT
31 JUL 2026202607310250902110$17.00$18.426ARRINGTON CURB & EXCAVATION, INC.ALDOT
26 JUN 2026202606260270601120$50.00$19.003ASPHALT CONTRACTORS, INC.ALDOT
26 JUN 202620260626029060136$25.00$25.005DUBOSE CONSTRUCTION COMPANY, LLCALDOT
26 JUN 202620260626035090244$25.21$25.215WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 20262026052900106033,172$31.59$29.433APAC-ALABAMA, INC.ALDOT
29 MAY 2026202605290230301254$69.38$123.304WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 20262026052904007045$7.00$55.153APAC-ALABAMA, INC.ALDOT
24 APR 20262026042400706042,366$5.00$9.345S. A. GRAHAM COMPANY, INC.ALDOT
24 APR 2026202604240440604111$15.81$16.563WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 20262026032700106064,121$12.96$13.702NEWELL & BUSH, INC.ALDOT
Latest ALDOT contracts carrying Structure Excavation

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy