Open Graded Friction Course Tack Coat unit price, Alabama

Low bidders on ALDOT contracts carried a median of $6.51 per GAL for item 420B000, open graded friction course tack coat, over the 24 months to 28 AUG 2026, across 34 low bids. Half of all 84 bids fell between $5.94 and $9.36.

Owner
Alabama DOT
Item
420B000
Unit
GAL
Latest letting
28 AUG 2026
$6.51Low bidder's median, per GAL
$6.86Median of all bids, per GAL
34Contracts in the window

By year of letting

Open Graded Friction Course Tack Coat, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221515$7.0034$7.74
20231717$8.0241$7.41
20241616$6.7337$7.42
20251717$6.4640$6.66
202677$8.6922$8.36
Open Graded Friction Course Tack Coat, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Open Graded Friction Course Tack Coat, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
03013$6.369$6.90
06034$7.629$7.50
10084$6.159$6.15
08043$6.786$7.27
Open Graded Friction Course Tack Coat, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Open Graded Friction Course Tack Coat, ALDOT: low bidder's median by quantity band
Quantity (GAL)Low bidsLow-bid median
378 to 8,1728$12.68
10,861 to 28,0409$6.40
30,109 to 48,9988$6.62
49,159 to 143,8009$5.91
Open Graded Friction Course Tack Coat, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Open Graded Friction Course Tack Coat
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 202620260828021100867,224$6.02$6.023DUNN CONSTRUCTION COMPANY, INC.ALDOT
28 AUG 202620260828023060121,215$10.00$7.332APAC-ALABAMA, INC.ALDOT
29 MAY 202620260529001060321,278$8.69$8.693APAC-ALABAMA, INC.ALDOT
24 APR 2026202604240070604378$36.40$36.105S. A. GRAHAM COMPANY, INC.ALDOT
27 MAR 20262026032700106063,572$16.44$17.282NEWELL & BUSH, INC.ALDOT
30 JAN 20262026013000305043,107$6.00$6.003MCINNIS CONSTRUCTION, LLCALDOT
30 JAN 202620260130033010210,861$6.40$6.634ROGERS GROUP, INC.ALDOT
05 DEC 20252025120505502045,266$21.45$11.184WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
07 NOV 202520251107022090170,280$5.66$6.432APAC-ALABAMA, INC.ALDOT
07 NOV 202520251107023090159,311$5.62$6.422APAC-ALABAMA, INC.ALDOT
07 NOV 202520251107026100863,941$6.29$6.293WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
26 SEP 202520250926018030125,750$6.36$6.363APAC-ALABAMA, INC.ALDOT
26 SEP 202520250926019040540,735$9.30$8.482VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
29 AUG 2025202508290070302143,800$5.13$6.174DUNN CONSTRUCTION COMPANY, INC.ALDOT
29 AUG 2025202508290110201, 04044,931$12.03$7.762APAC-ALABAMA, INC.ALDOT
Latest ALDOT contracts carrying Open Graded Friction Course Tack Coat

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy