Smoothness Testing, Certified Inertial Profiler unit price, Alabama
Low bidders on ALDOT contracts carried a median of $5,000.00 per EACH for item 410I000, smoothness testing, certified inertial profiler, over the 24 months to 28 AUG 2026, across 37 low bids. Half of all 102 bids fell between $3,348.25 and $9,638.37.
- Owner
- Alabama DOT
- Item
- 410I000
- Unit
- EACH
- Latest letting
- 28 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 24 | 24 | $8,323.58 | 49 | $9,400.00 |
| 2023 | 24 | 24 | $5,288.68 | 60 | $7,078.00 |
| 2024 | 20 | 20 | $7,474.84 | 49 | $6,192.93 |
| 2025 | 21 | 21 | $5,472.03 | 65 | $5,363.04 |
| 2026 | 9 | 7 | $2,998.00 | 19 | $5,000.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| 0301 | 3 | $6,600.00 | 16 | $5,247.40 |
| 0305 | 4 | $3,783.77 | 12 | $3,530.16 |
| 0202 | 3 | $1,500.00 | 8 | $8,046.66 |
| 1008 | 3 | $2,861.57 | 6 | $3,518.43 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 9 | $7,671.40 |
| 1 to 1 | 9 | $4,696.54 |
| 1 to 1 | 9 | $5,000.00 |
| 1 to 1 | 10 | $4,246.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 AUG 2026 | 20260828023 | 0601 | 1 | $2,850.00 | $6,425.00 | 2 | APAC-ALABAMA, INC. | ALDOT |
| 31 JUL 2026 | 20260731011 | 0105 | 1 | $5,000.00 | $5,000.00 | 3 | VULCAN MATERIALS ASPHALT AND CONSTRUCTION, | ALDOT |
| 29 MAY 2026 | 20260529001 | 0603 | 1 | n/a | $10,112 | 2 | APAC-ALABAMA, INC. | ALDOT |
| 24 APR 2026 | 20260424007 | 0604 | 1 | n/a | $5,775.00 | 1 | S. A. GRAHAM COMPANY, INC. | ALDOT |
| 24 APR 2026 | 20260424044 | 0604 | 1 | $3,493.00 | $2,479.14 | 2 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 27 FEB 2026 | 20260227021 | 0202 | 1 | $1,500.00 | $4,750.00 | 2 | ROGERS GROUP, INC. | ALDOT |
| 30 JAN 2026 | 20260130003 | 0504 | 1 | $2,998.00 | $2,998.00 | 3 | MCINNIS CONSTRUCTION, LLC | ALDOT |
| 30 JAN 2026 | 20260130023 | 0201 | 1 | $1,500.00 | $5,297.64 | 3 | ROGERS GROUP, INC. | ALDOT |
| 30 JAN 2026 | 20260130031 | 0401 | 1 | $27,321 | $27,321 | 1 | GARY INGRAM GRADING & PAVING, INC. | ALDOT |
| 07 NOV 2025 | 20251107020 | 0506 | 1 | $7,340.86 | $7,340.86 | 1 | S. T. BUNN CONSTRUCTION COMPANY, INC. | ALDOT |
| 07 NOV 2025 | 20251107038 | 0404 | 1 | $23,857 | $23,857 | 1 | GARY INGRAM GRADING & PAVING, INC. | ALDOT |
| 26 SEP 2025 | 20250926018 | 0301 | 1 | $11,300 | $5,131.75 | 3 | APAC-ALABAMA, INC. | ALDOT |
| 29 AUG 2025 | 20250829022 | 0301 | 1 | $4,437.12 | $4,495.56 | 6 | CHILTON CONTRACTORS, INC. | ALDOT |
| 25 JUL 2025 | 20250725001 | 0301 | 1 | $6,600.00 | $7,056.00 | 7 | GILLESPIE CONSTRUCTION, LLC | ALDOT |
| 25 JUL 2025 | 20250725008 | 0103 | 1 | $23,000 | $9,272.00 | 4 | ROGERS GROUP, INC. | ALDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.
How these prices were read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.