Superpave Bituminous Concrete Upper Binder Layer, Patching, 1" Maximum Aggregate Size Mix, ESAL Range A/B unit price, Alabama
Low bidders on ALDOT contracts carried a median of $150.00 per TON for item 424B640, superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range a/b, over the 24 months to 28 AUG 2026, across 39 low bids. Half of all 104 bids fell between $125.00 and $210.75.
- Owner
- Alabama DOT
- Item
- 424B640
- Unit
- TON
- Latest letting
- 26 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 17 | 17 | $175.00 | 43 | $201.34 |
| 2023 | 16 | 16 | $185.15 | 37 | $195.07 |
| 2024 | 21 | 21 | $142.00 | 54 | $153.89 |
| 2025 | 16 | 16 | $147.50 | 43 | $135.96 |
| 2026 | 17 | 17 | $155.55 | 45 | $175.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| 0601 | 6 | $119.09 | 20 | $142.50 |
| 0201 | 4 | $109.10 | 12 | $103.35 |
| 0704 | 4 | $172.51 | 12 | $188.44 |
| 0804 | 3 | $169.25 | 6 | $169.58 |
| 0706 | 3 | $213.65 | 6 | $194.58 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 20 to 100 | 9 | $185.00 |
| 100 to 150 | 10 | $157.35 |
| 150 to 500 | 10 | $159.50 |
| 500 to 1,500 | 10 | $126.07 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 JUN 2026 | 20260626017 | 0204 | 1,500 | $95.06 | $98.00 | 3 | GRAYSON CARTER & SON CONTRACTING, INC. | ALDOT |
| 26 JUN 2026 | 20260626022 | 0803 | 500 | $147.50 | $163.34 | 2 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 26 JUN 2026 | 20260626027 | 0601 | 50 | $120.00 | $200.00 | 3 | ASPHALT CONTRACTORS, INC. | ALDOT |
| 26 JUN 2026 | 20260626029 | 0601 | 100 | $150.00 | $152.66 | 5 | DUBOSE CONSTRUCTION COMPANY, LLC | ALDOT |
| 26 JUN 2026 | 20260626032 | 0606 | 500 | $216.76 | $216.76 | 1 | EAST ALABAMA PAVING COMPANY, INC. | ALDOT |
| 29 MAY 2026 | 20260529037 | 0402 | 75 | $139.91 | $220.00 | 3 | ALABAMA GRADING & EXCAVATION, LLC. | ALDOT |
| 24 APR 2026 | 20260424028 | 0804 | 500 | $169.25 | $180.13 | 2 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 24 APR 2026 | 20260424038 | 0601 | 150 | $118.17 | $140.00 | 3 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 27 MAR 2026 | 20260327025 | 0706 | 100 | $213.65 | $199.51 | 2 | APAC-ALABAMA, INC. | ALDOT |
| 27 MAR 2026 | 20260327030 | 0706 | 100 | $203.79 | $189.39 | 2 | APAC-ALABAMA, INC. | ALDOT |
| 27 MAR 2026 | 20260327038 | 0704 | 100 | $164.70 | $200.00 | 3 | WIREGRASS CONSTRUCTION COMPANY, INC. | ALDOT |
| 27 MAR 2026 | 20260327040 | 0706 | 100 | $217.90 | $193.95 | 2 | APAC-ALABAMA, INC. | ALDOT |
| 27 FEB 2026 | 20260227031 | 0804 | 200 | $169.92 | $244.48 | 2 | APAC-ALABAMA, INC. | ALDOT |
| 30 JAN 2026 | 20260130045 | 0702 | 100 | $128.00 | $175.00 | 3 | SOUTHEAST CONSTRUCTION COMPANY, LLC | ALDOT |
| 30 JAN 2026 | 20260130049 | 0201 | 750 | $155.55 | $170.00 | 3 | ASPHALT PAVING SYSTEMS INC | ALDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.
How these prices were read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.