Mineral aggregate in achm surface course (3/8") unit price, Arkansas
Low bidders on ARDOT contracts carried a median of $121.00 per TON for item 407161, mineral aggregate in achm surface course (3/8"), over the 24 months to 04 NOV 2026, across 136 low bids. Half of all 378 bids fell between $98.50 and $155.17.
- Owner
- Arkansas DOT
- Item
- 407161
- Unit
- TON
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 84 | 84 | $104.50 | 147 | $105.00 |
| 2023 | 106 | 106 | $130.75 | 186 | $128.57 |
| 2024 | 83 | 83 | $122.00 | 170 | $128.86 |
| 2025 | 67 | 67 | $124.42 | 195 | $125.00 |
| 2026 | 65 | 65 | $115.00 | 171 | $123.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Craighead | 5 | $92.57 | 16 | $97.16 |
| Benton | 5 | $101.00 | 15 | $110.25 |
| Jackson | 3 | $100.07 | 15 | $105.00 |
| Mississippi | 4 | $142.24 | 13 | $123.50 |
| Crittenden | 3 | $111.10 | 12 | $127.83 |
| Dallas | 3 | $136.50 | 10 | $147.50 |
| Logan | 3 | $102.13 | 9 | $134.00 |
| Miller | 3 | $179.77 | 8 | $179.88 |
| Pulaski | 3 | $113.00 | 8 | $124.45 |
| Prairie | 3 | $125.60 | 8 | $129.90 |
| Independence | 3 | $93.83 | 7 | $91.40 |
| Carroll | 3 | $101.51 | 6 | $104.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 47 to 939 | 34 | $162.75 |
| 961 to 2,122 | 34 | $126.14 |
| 2,186 to 4,155 | 34 | $121.15 |
| 4,183 to 35,619 | 34 | $97.14 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A50052 | Independence | 12,934 | $91.40 | $65.11 | 2 | ATLAS ASPHALT, INC. | ARDOT |
| 04 NOV 2026 | A90050 | Baxter | 19,797 | $88.68 | $90.84 | 2 | ATLAS ASPHALT, INC. | ARDOT |
| 23 SEP 2026 | 061950 | Pulaski | 3,117 | $113.00 | $134.12 | 2 | REDSTONE CONSTRUCTION GROUP, LLC | ARDOT |
| 23 SEP 2026 | SA2046 | Dallas | 1,610 | $146.00 | $146.00 | 3 | REDSTONE CONSTRUCTION GROUP, LLC | ARDOT |
| 24 JUN 2026 | C09008 | Chicot | 1,580 | $162.26 | $216.75 | 2 | PINE BLUFF SAND & GRAVEL CO. | ARDOT |
| 24 JUN 2026 | SA0148 | Arkansas | 786 | $146.03 | $160.19 | 3 | ATLAS ASPHALT, INC. | ARDOT |
| 24 JUN 2026 | SA3056 | Hot Spring | 3,934 | $91.00 | $115.03 | 2 | REDSTONE CONSTRUCTION GROUP, INC. | ARDOT |
| 24 JUN 2026 | SA3466 | Jackson | 3,094 | $100.28 | $105.12 | 4 | ATLAS ASPHALT, INC. | ARDOT |
| 24 JUN 2026 | SA4051 | Lincoln | 3,039 | $126.64 | $130.94 | 2 | PINE BLUFF SAND & GRAVEL CO. | ARDOT |
| 24 JUN 2026 | SA5955 | Prairie | 216 | $221.00 | $221.00 | 1 | SALT CREEK PAVING & CONST. CO., INC. | ARDOT |
| 24 JUN 2026 | SA5956 | Prairie | 784 | $125.60 | $125.60 | 5 | REDSTONE CONSTRUCTION GROUP, INC. | ARDOT |
| 20 MAY 2026 | A10052 | Lee, Monroe | 4,985 | $119.91 | $119.91 | 5 | M & T PAVING & CONST. CO., INC. | ARDOT |
| 20 MAY 2026 | A70042 | Calhoun, Dallas | 19,320 | $127.85 | $133.93 | 2 | REDSTONE CONSTRUCTION GROUP, INC. | ARDOT |
| 20 MAY 2026 | A00095 | Craighead | 3,907 | $98.14 | $98.14 | 3 | ATLAS ASPHALT, INC. | ARDOT |
| 20 MAY 2026 | C59009 | Prairie | 2,525 | $98.13 | $119.52 | 2 | CK ASPHALT, LLC | ARDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.
How these prices were read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.