Mineral aggregate in achm base course (1 1/2") unit price, Arkansas

Low bidders on ARDOT contracts carried a median of $130.00 per TON for item 405161, mineral aggregate in achm base course (1 1/2"), over the 24 months to 04 NOV 2026, across 25 low bids. Half of all 91 bids fell between $95.75 and $175.35.

Owner
Arkansas DOT
Item
405161
Unit
TON
Latest letting
04 NOV 2026
$130.00Low bidder's median, per TON
$138.98Median of all bids, per TON
25Contracts in the window

By year of letting

Mineral aggregate in achm base course (1 1/2"), ARDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221111$150.0026$133.25
20231515$160.0035$165.63
20241211$140.0024$143.00
20251515$109.0052$119.67
202699$138.9837$149.72
Mineral aggregate in achm base course (1 1/2"), ARDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Mineral aggregate in achm base course (1 1/2"), ARDOT: low bidder's median by quantity band
Quantity (TON)Low bidsLow-bid median
38 to 3686$183.25
419 to 1,4426$130.62
1,953 to 2,5796$94.50
3,554 to 18,3217$138.98
Mineral aggregate in achm base course (1 1/2"), ARDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ARDOT contracts carrying Mineral aggregate in achm base course (1 1/2")
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
04 NOV 2026040904Crawford8,689$149.72$153.344CROSSLAND CONSTRUCTION CO., INC.ARDOT
04 NOV 2026061922Garland136$220.00$372.502TI-ZACK CONCRETE, LLCARDOT
04 NOV 2026101141Mississippi606$131.25$191.254BLUFF CITY CONSTRUCTION CO., LLCARDOT
23 SEP 2026070458Columbia3,554$156.01$150.007MOBLEY CONTRACTORS, INC.ARDOT
12 AUG 2026030531Little River10,444$138.98$146.066MCGEORGE CONTRACTING CO., INC.ARDOT
12 AUG 2026090702Benton317$146.50$146.503APAC-CENTRAL, INC.ARDOT
04 MAR 2026A00097Clay2,175$83.93$79.682DELTA ASPHALT OF ARKANSAS, INC.ARDOT
21 JAN 2026061371Lonoke12,959$65.67$65.844WEAVER-BAILEY CONTRACTORS, INC.ARDOT
21 JAN 2026061371Lonoke202n/a$64.002WEAVER-BAILEY CONTRACTORS, INC.ARDOT
21 JAN 2026100881Craighead1,997$78.00$101.273ROGERS GROUP, INC.ARDOT
05 NOV 2025A50047Cleburne537$69.75$69.753CK ASPHALT, LLCARDOT
05 NOV 2025090433Benton1,953$99.00$121.604GRANT GARRETT EXCAVATING, INC.ARDOT
05 NOV 2025090651Benton95$122.00$257.504GRANT GARRETT EXCAVATING, INC.ARDOT
15 OCT 2025040746Washington18,321$109.00$107.753APAC-CENTRAL, INC.ARDOT
17 SEP 2025040889Sebastian1,442$149.65$252.322FORSGREN, INC.ARDOT
Latest ARDOT contracts carrying Mineral aggregate in achm base course (1 1/2")

Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.

How these prices were read

ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy