Sand bag ditch checks unit price, Arkansas

Low bidders on ARDOT contracts carried a median of $10.90 per BAG for item 621031, sand bag ditch checks, over the 24 months to 04 NOV 2026, across 68 low bids. Half of all 245 bids fell between $10.00 and $13.89.

Owner
Arkansas DOT
Item
621031
Unit
BAG
Latest letting
04 NOV 2026
$10.90Low bidder's median, per BAG
$11.86Median of all bids, per BAG
69Contracts in the window

By year of letting

Sand bag ditch checks, ARDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20223636$10.0097$10.00
20233535$10.0077$10.38
20244342$10.00101$10.00
20252626$11.0391$12.00
20263939$10.86142$11.45
Sand bag ditch checks, ARDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Sand bag ditch checks, ARDOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Benton4$13.7017$14.39
Crawford4$10.3512$10.95
Prairie3$11.8612$12.56
Craighead4$10.3812$10.38
Baxter3$10.9311$10.93
Sand bag ditch checks, ARDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Sand bag ditch checks, ARDOT: low bidder's median by quantity band
Quantity (BAG)Low bidsLow-bid median
20 to 17817$12.00
185 to 33017$11.98
352 to 70017$11.29
800 to 6,88617$9.96
Sand bag ditch checks, ARDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ARDOT contracts carrying Sand bag ditch checks
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
04 NOV 2026A10059Phillips20$1.00$1.001ATLAS ASPHALT, INC.ARDOT
04 NOV 2026A20044Arkansas700$10.00$10.154PINE BLUFF SAND & GRAVEL CO.ARDOT
04 NOV 2026040904Crawford6,886$10.70$10.794CROSSLAND CONSTRUCTION CO., INC.ARDOT
04 NOV 2026A40062Polk475$13.05$13.051BLACKSTONE CONSTRUCTION, LLCARDOT
04 NOV 2026061922Garland220$11.98$13.492TI-ZACK CONCRETE, LLCARDOT
04 NOV 2026A70050Clark200$15.10$14.482REDSTONE CONSTRUCTION GROUP, LLCARDOT
04 NOV 2026101141Mississippi264$12.60$12.294BLUFF CITY CONSTRUCTION CO., LLCARDOT
04 NOV 2026BR4401Madison396$11.29$11.295WEST PLAINS BR. & GRADING, LLCARDOT
04 NOV 2026FA0314Baxter110$13.89$13.893ROBERTSON CONTRACTORS, INC.ARDOT
23 SEP 2026110716Phillips110$15.00$13.0081911 CONSTRUCTION COMPANY, INC.ARDOT
23 SEP 2026061921Pulaski198$13.05$15.753TI-ZACK CONCRETE, LLCARDOT
23 SEP 2026070458Columbia264$10.50$10.757MOBLEY CONTRACTORS, INC.ARDOT
23 SEP 2026012559Craighead, Crittenden110$8.00$11.972SHELBY ELECTRIC COMPANY, INC.ARDOT
23 SEP 2026CB0401Benton44$14.39$16.186MOBLEY CONTRACTORS, INC.ARDOT
12 AUG 2026090702Benton616$12.70$12.703APAC-CENTRAL, INC.ARDOT
Latest ARDOT contracts carrying Sand bag ditch checks

Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.

How these prices were read

ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy