Sediment basin unit price, Arkansas
Low bidders on ARDOT contracts carried a median of $11.68 per CY for item 621071, sediment basin, over the 24 months to 04 NOV 2026, across 24 low bids. Half of all 104 bids fell between $5.00 and $26.52.
- Owner
- Arkansas DOT
- Item
- 621071
- Unit
- CY
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 22 | 22 | $9.00 | 63 | $11.00 |
| 2023 | 21 | 21 | $9.73 | 48 | $10.00 |
| 2024 | 25 | 24 | $11.25 | 66 | $12.00 |
| 2025 | 10 | 10 | $13.79 | 39 | $14.84 |
| 2026 | 13 | 13 | $8.95 | 61 | $8.95 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 20 to 100 | 6 | $11.34 |
| 100 to 200 | 6 | $10.47 |
| 250 to 586 | 6 | $12.30 |
| 600 to 5,533 | 6 | $15.73 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | 040904 | Crawford | 5,533 | $3.99 | $8.01 | 4 | CROSSLAND CONSTRUCTION CO., INC. | ARDOT |
| 04 NOV 2026 | 101141 | Mississippi | 100 | $8.95 | $19.48 | 4 | BLUFF CITY CONSTRUCTION CO., LLC | ARDOT |
| 04 NOV 2026 | BR4401 | Madison | 111 | $1.00 | $2.00 | 5 | WEST PLAINS BR. & GRADING, LLC | ARDOT |
| 04 NOV 2026 | FA0314 | Baxter | 311 | $14.15 | $14.15 | 3 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 23 SEP 2026 | 110716 | Phillips | 133 | $12.00 | $6.50 | 8 | 1911 CONSTRUCTION COMPANY, INC. | ARDOT |
| 23 SEP 2026 | 070458 | Columbia | 2,117 | $5.88 | $8.00 | 7 | MOBLEY CONTRACTORS, INC. | ARDOT |
| 24 JUN 2026 | BR2814 | Greene | 444 | $5.00 | $10.00 | 7 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 08 APR 2026 | A50044 | Stone | 40 | $11.37 | $11.37 | 1 | ATLAS ASPHALT, INC. | ARDOT |
| 04 MAR 2026 | 020738 | Arkansas | 100 | $5.25 | $11.12 | 4 | MOBLEY CONTRACTORS, INC. | ARDOT |
| 04 MAR 2026 | 101003 | Randolph | 586 | $1.77 | $5.00 | 5 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 21 JAN 2026 | 061371 | Lonoke | 250 | $58.79 | $54.08 | 4 | WEAVER-BAILEY CONTRACTORS, INC. | ARDOT |
| 21 JAN 2026 | 100881 | Craighead | 600 | $27.00 | $23.06 | 2 | ROGERS GROUP, INC. | ARDOT |
| 21 JAN 2026 | FA1108 | Clay | 1,800 | $16.62 | $3.00 | 7 | DELTA ASPHALT OF ARKANSAS, INC. | ARDOT |
| 05 NOV 2025 | 090672 | Searcy | 20 | $4.00 | $7.75 | 6 | CROUSE CONSTRUCTION CO. | ARDOT |
| 05 NOV 2025 | 101091 | Craighead | 100 | $13.44 | $13.44 | 3 | KESSER INTERNATIONAL, INC. | ARDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.
How these prices were read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.