Stone backfill unit price, Arkansas

Low bidders on ARDOT contracts carried a median of $82.50 per TON for item 207011, stone backfill, over the 24 months to 04 NOV 2026, across 26 low bids. Half of all 111 bids fell between $65.94 and $117.22.

Owner
Arkansas DOT
Item
207011
Unit
TON
Latest letting
04 NOV 2026
$82.50Low bidder's median, per TON
$85.00Median of all bids, per TON
26Contracts in the window

By year of letting

Stone backfill, ARDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202255$38.0016$48.00
202377$69.3915$82.50
20241010$69.4428$80.00
202588$88.2034$96.88
20261515$85.0068$83.04
Stone backfill, ARDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Stone backfill, ARDOT: low bidder's median by quantity band
Quantity (TON)Low bidsLow-bid median
30 to 506$107.40
50 to 2507$138.00
260 to 5246$74.14
533 to 16,3157$63.74
Stone backfill, ARDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ARDOT contracts carrying Stone backfill
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
04 NOV 2026040904Crawford16,315$36.36$40.014CROSSLAND CONSTRUCTION CO., INC.ARDOT
04 NOV 2026101141Mississippi45$121.00$102.024BLUFF CITY CONSTRUCTION CO., LLCARDOT
23 SEP 2026110716Phillips2,256$80.00$96.4181911 CONSTRUCTION COMPANY, INC.ARDOT
24 JUN 2026BR2814Greene260$85.00$106.427ROBERTSON CONTRACTORS, INC.ARDOT
20 MAY 2026SA6347Scott50$186.88$145.004BLACKSTONE CONSTRUCTION, LLCARDOT
08 APR 2026110751Lee524$69.88$70.748WHITE RIVER MATERIALS, INC.ARDOT
08 APR 2026101115Randolph50$85.00$90.004KYNERIC, LLCARDOT
08 APR 2026C76092Hot Spring, Saline50$140.00$188.833REDSTONE CONSTRUCTION GROUP, INC.ARDOT
08 APR 2026SA2138Desha170$190.70$177.852SALT CREEK PAVING & CONST. CO., INC.ARDOT
04 MAR 2026A50045White250$65.00$72.504CK ASPHALT, LLCARDOT
04 MAR 2026101100Greene455$55.00$85.364ROBERTSON CONTRACTORS, INC.ARDOT
21 JAN 2026061371Lonoke165$109.26$114.634WEAVER-BAILEY CONTRACTORS, INC.ARDOT
21 JAN 2026A80046Faulkner87$64.00$59.502ROGERS GROUP, INC.ARDOT
21 JAN 2026AX0008Jackson, Lonoke, White1,500$225.00$139.203ROGERS GROUP, INC.ARDOT
21 JAN 2026FA1108Clay533$63.74$63.747DELTA ASPHALT OF ARKANSAS, INC.ARDOT
Latest ARDOT contracts carrying Stone backfill

Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.

How these prices were read

ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way