Bollards unit price, Florida

Low bidders on FDOT contracts carried a median of $1,326.56 per EACH for item 0519-78, bollards, over the 24 months to 28 OCT 2026, across 15 low bids. Half of all 87 bids fell between $927.92 and $2,482.50.

Owner
Florida DOT
Item
0519-78
Unit
EACH
Latest letting
28 OCT 2026
$1,326.56Low bidder's median, per EACH
$1,397.18Median of all bids, per EACH
15Contracts in the window

By year of letting

Bollards, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201833$1,100.0017$775.00
201966$911.2226$951.03
202022$672.509$686.81
202167$750.0039$612.00
202233$1,160.009$1,160.00
202357$1,127.0020$1,473.20
202433$1,000.0010$1,075.00
202544$1,677.5022$1,810.00
20261010$1,371.0763$1,326.39
Bollards, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Bollards, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 74$1,371.0723$1,415.57
District 43$1,000.0020$1,375.32
District 53$3,215.0019$1,450.00
Bollards, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Bollards, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
3 to 43$1,035.00
5 to 74$3,057.78
14 to 194$802.50
30 to 1384$1,750.00
Bollards, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Bollards
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T2A73District 24$1,035.00$1,080.008C.W. ROBERTS CONTRACTING, INC.FDOT
29 JUL 2026T5883District 5138$850.00$1,300.009MASCI GENERAL CONTRACTORS, INCFDOT
29 JUL 2026T7619District 76$1,415.57$1,457.786TURTLE INFRASTRUCTURE PARTNERS, LLCFDOT
15 JUN 2026T5885District 55$6,266.00$3,200.004C.W. ROBERTS CONTRACTING, INC.FDOT
10 JUN 2026T5884District 516$3,215.00$1,537.506C.W. ROBERTS CONTRACTING, INC.FDOT
10 JUN 2026T7534District 73$1,913.60$1,696.664PREFERRED MATERIALS INC.FDOT
29 APR 2026T4738District 437$1,000.00$1,000.007OHLA USA INCFDOT
29 APR 2026T7562District 715$750.00$1,181.717WATSON CIVIL CONSTRUCTION, INC.FDOT
25 MAR 2026T1920District 16$4,700.00$1,170.006SEMA CONSTRUCTION, INC.FDOT
25 FEB 2026T7601District 77$1,326.56$1,465.386PREFERRED MATERIALS INC.FDOT
03 DEC 2025T4729District 484$5,500.00$6,442.398WEBBER, LLCFDOT
24 SEP 2025T2A24District 230$2,500.00$1,810.008MASTEC CIVIL LLCFDOT
26 MAR 2025T9042StateWide4$855.00$855.001E. B. MORRIS GENERAL CONTRACTORS, INC.FDOT
26 FEB 2025T4712District 414$825.00$1,500.005GENERAL ASPHALT COMPANY, LLCFDOT
04 DEC 2024T3931District 319$780.00$835.492C.W. ROBERTS CONTRACTING, INC.FDOT
Latest FDOT contracts carrying Bollards

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way