Pedestrian / bicycle railing, steel, 42" type 1 unit price, Florida
Low bidders on FDOT contracts carried a median of $153.44 per LF for item 0515-2211, pedestrian / bicycle railing, steel, 42" type 1, over the 24 months to 28 OCT 2026, across 6 low bids. Half of all 42 bids fell between $121.88 and $198.53.
- Owner
- Florida DOT
- Item
- 0515-2211
- Unit
- LF
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 4 | 4 | $99.00 | 18 | $82.25 |
| 2019 | 10 | 10 | $107.04 | 43 | $106.00 |
| 2020 | 7 | 8 | $83.50 | 41 | $92.00 |
| 2021 | 4 | 4 | $105.50 | 19 | $105.00 |
| 2022 | 7 | 7 | $133.31 | 28 | $142.50 |
| 2023 | 9 | 10 | $135.44 | 47 | $143.19 |
| 2024 | 2 | 2 | $206.31 | 8 | $312.61 |
| 2025 | 2 | 2 | $228.37 | 10 | $223.45 |
| 2026 | 4 | 4 | $110.75 | 32 | $127.28 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 7 | 15 | $121.00 | 72 | $118.00 |
| District 4 | 10 | $125.00 | 66 | $156.62 |
| District 2 | 11 | $120.00 | 35 | $125.00 |
| District 1 | 7 | $104.00 | 32 | $104.50 |
| District 5 | 5 | $105.90 | 31 | $115.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 1 to 72 | 12 | $134.16 |
| 74 to 232 | 13 | $121.47 |
| 274 to 589 | 13 | $92.75 |
| 651 to 6,561 | 13 | $106.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T2A84 | District 2 | 20 | $185.39 | $175.34 | 7 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 20 MAY 2026 | T4666 | District 4 | 171 | $100.00 | $144.28 | 8 | OHLA USA INC | FDOT |
| 20 MAY 2026 | T5882 | District 5 | 200 | $121.50 | $122.45 | 10 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 29 APR 2026 | T7562 | District 7 | 674 | $99.00 | $117.00 | 7 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 27 AUG 2025 | T4715 | District 4 | 8 | $225.00 | $221.90 | 9 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A BC&E | FDOT |
| 28 MAY 2025 | T2A20 | District 2 | 488 | $231.73 | $231.73 | 1 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 22 MAY 2024 | T1865 | District 1 | 6,561 | $106.66 | $105.00 | 3 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 31 JAN 2024 | T4643 | District 4 | 7 | $305.97 | $323.00 | 5 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 13 SEP 2023 | T6413 | District 6, Turnpike | 848 | $189.75 | $179.88 | 2 | GGI CONSTRUCTORS JV | FDOT |
| 14 JUN 2023 | T1861 | District 1 | 4,621 | $143.19 | $127.50 | 6 | ZEP CONSTRUCTION, INC. | FDOT |
| 14 JUN 2023 | T2958 | District 2 | 1,502 | $106.00 | $137.00 | 3 | SUPERIOR CONSTRUCTION COMPANY SOUTHEAST, LLC | FDOT |
| 14 JUN 2023 | T2958 | District 2 | 545 | $128.00 | $154.55 | 3 | SUPERIOR CONSTRUCTION COMPANY SOUTHEAST, LLC | FDOT |
| 14 JUN 2023 | T7516 | District 7 | 62 | $130.00 | $150.00 | 5 | BURGESS CIVIL, LLC | FDOT |
| 24 MAY 2023 | T5789 | District 5 | 795 | $105.90 | $135.00 | 6 | RANGER CONSTRUCTION INDUSTRIES, INC. | FDOT |
| 24 MAY 2023 | T7505 | District 7 | 40 | $140.87 | $225.00 | 7 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way