Electrical power service, f&i, underground, meter not required unit price, Florida
Low bidders on FDOT contracts carried a median of $5,633.72 per AS for item 0639-1123, electrical power service, f&i, underground, meter not required, over the 24 months to 28 OCT 2026, across 18 low bids. Half of all 119 bids fell between $4,568.33 and $7,000.00.
- Owner
- Florida DOT
- Item
- 0639-1123
- Unit
- AS
- Latest letting
- 30 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 8 | 8 | $1,670.35 | 41 | $2,000.00 |
| 2019 | 7 | 7 | $1,566.00 | 29 | $2,260.65 |
| 2020 | 2 | 2 | $2,765.00 | 5 | $2,521.19 |
| 2021 | 13 | 13 | $2,198.79 | 55 | $2,800.00 |
| 2022 | 12 | 12 | $3,176.00 | 35 | $3,850.00 |
| 2023 | 9 | 9 | $4,141.28 | 31 | $4,322.46 |
| 2024 | 4 | 4 | $5,075.00 | 14 | $5,034.50 |
| 2025 | 5 | 5 | $7,459.98 | 37 | $5,623.34 |
| 2026 | 11 | 13 | $5,626.85 | 82 | $5,405.37 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 6 | 5 | $7,142.75 | 38 | $5,475.20 |
| District 4 | 5 | $5,626.85 | 35 | $5,686.13 |
| District 5 | 3 | $21,068 | 21 | $10,141 |
| District 7 | 3 | $5,633.72 | 18 | $5,250.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (AS) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 4 | $5,214.80 |
| 1 to 1 | 5 | $4,000.00 |
| 1 to 2 | 4 | $5,633.72 |
| 2 to 62 | 5 | $7,635.32 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 SEP 2026 | T5893 | District 5 | 1 | $2,408.05 | $2,600.00 | 8 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 30 SEP 2026 | T6398 | District 6 | 1 | $7,142.75 | $7,410.00 | 4 | OHLA USA INC | FDOT |
| 29 JUL 2026 | T5883 | District 5 | 2 | $21,068 | $20,600 | 9 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 29 JUL 2026 | T6595 | District 6 | 1 | $4,000.00 | $4,807.00 | 12 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A BC&E | FDOT |
| 15 JUN 2026 | T5885 | District 5 | 62 | $23,272 | $23,336 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 20 MAY 2026 | T7607 | District 7 | 1 | $1,749.60 | $5,200.00 | 6 | BLACKTIP SERVICES INCORPORATED | FDOT |
| 20 MAY 2026 | T7607 | District 7 | 1 | $5,633.72 | $5,348.81 | 6 | BLACKTIP SERVICES INCORPORATED | FDOT |
| 20 MAY 2026 | T7607 | District 7 | 1 | $5,633.72 | $5,298.81 | 6 | BLACKTIP SERVICES INCORPORATED | FDOT |
| 25 MAR 2026 | T4734 | District 4 | 2 | $5,626.85 | $5,686.13 | 7 | SICE INC | FDOT |
| 25 MAR 2026 | T4735 | District 4 | 2 | $4,618.11 | $5,241.30 | 6 | SICE INC | FDOT |
| 25 MAR 2026 | T6591 | District 6 | 2 | $6,500.00 | $5,475.20 | 7 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
| 25 FEB 2026 | T2A36 | District 2 | 1 | $3,429.59 | $3,964.80 | 2 | CHINCHOR ELECTRIC INC. | FDOT |
| 28 JAN 2026 | T2A56 | District 2 | 1 | $5,194.00 | $5,585.00 | 5 | DE MOYA CONTRACTING LLC | FDOT |
| 03 DEC 2025 | T6615 | District 6 | 2 | $8,080.49 | $5,363.59 | 8 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 27 AUG 2025 | T4702 | District 4 | 1 | $2,840.20 | $2,883.20 | 8 | THE STOUT GROUP LLC | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.