Guardrail reset unit price, Florida
Low bidders on FDOT contracts carried a median of $14.87 per LF for item 0538-1, guardrail reset, over the 24 months to 28 OCT 2026, across 10 low bids. Half of all 51 bids fell between $14.36 and $20.01.
- Owner
- Florida DOT
- Item
- 0538-1
- Unit
- LF
- Latest letting
- 20 MAY 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 7 | 7 | $11.50 | 31 | $9.00 |
| 2019 | 10 | 10 | $15.28 | 31 | $15.00 |
| 2020 | 6 | 6 | $11.58 | 26 | $10.70 |
| 2021 | 6 | 6 | $10.20 | 36 | $10.77 |
| 2022 | 5 | 5 | $25.65 | 21 | $12.72 |
| 2023 | 6 | 6 | $21.51 | 18 | $17.96 |
| 2024 | 9 | 9 | $20.84 | 32 | $21.00 |
| 2025 | 4 | 4 | $13.84 | 19 | $16.41 |
| 2026 | 4 | 4 | $14.87 | 25 | $15.60 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 MAY 2026 | T3991 | District 3 | 78 | $15.30 | $18.70 | 6 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 20 MAY 2026 | T4666 | District 4 | 1,020 | $14.43 | $14.91 | 8 | OHLA USA INC | FDOT |
| 20 MAY 2026 | T7587 | District 7 | 200 | $16.67 | $16.26 | 5 | HUBBARD CONSTRUCTION COMPANY | FDOT |
| 25 MAR 2026 | T5876 | District 5 | 1,771 | $14.09 | $14.25 | 6 | TIMOTHY ROSE CONTRACTING, INC. | FDOT |
| 30 JUL 2025 | T5860 | District 5 | 5,033 | $13.49 | $16.60 | 5 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 11 JUN 2025 | T3852 | District 3 | 420 | $14.00 | $13.90 | 6 | AMERICAN SAND & X-CAVATION, INC. DBA AMERICAN SAND & ASPHALT | FDOT |
| 26 MAR 2025 | T1910 | District 1 | 1,807 | $13.68 | $16.41 | 3 | PREFERRED MATERIALS INC. | FDOT |
| 26 FEB 2025 | T5857 | District 5 | 22 | $200.00 | $116.69 | 5 | HALIFAX PAVING, INC. | FDOT |
| 04 DEC 2024 | T5841 | District 5 | 118 | $17.31 | $17.31 | 3 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 13 NOV 2024 | T7541 | District 7 | 54 | $27.00 | $28.50 | 4 | BURGESS CIVIL, LLC | FDOT |
| 25 SEP 2024 | T5833 | District 5 | 384 | $47.00 | $47.00 | 3 | P & S PAVING, INC. | FDOT |
| 19 JUN 2024 | T7501 | District 7 | 4,091 | $20.84 | $21.00 | 4 | WEBBER, LLC | FDOT |
| 24 APR 2024 | T7520 | District 7 | 1,097 | $16.50 | $18.86 | 4 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 17 APR 2024 | T7531 | District 7 | 4,084 | $22.65 | $21.12 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 27 MAR 2024 | T1857 | District 1 | 1,050 | $13.50 | $13.50 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.