Guardrail end treatment- parallel approach terminal unit price, Florida

Low bidders on FDOT contracts carried a median of $3,500.00 per EACH for item 0536-85-24, guardrail end treatment- parallel approach terminal, over the 24 months to 28 OCT 2026, across 141 low bids. Half of all 643 bids fell between $3,200.00 and $3,891.55.

Owner
Florida DOT
Item
0536-85-24
Unit
EACH
Latest letting
28 OCT 2026
$3,500.00Low bidder's median, per EACH
$3,495.00Median of all bids, per EACH
141Contracts in the window

By year of letting

Guardrail end treatment- parallel approach terminal, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20183434$2,792.95156$2,888.75
20196363$3,050.00282$3,047.91
20204949$2,930.50250$2,956.81
20216565$3,177.50327$3,130.00
20226969$3,600.00228$3,667.75
20238181$3,844.49254$3,842.24
20246868$3,705.62256$3,648.35
20256767$3,500.00309$3,500.00
20266363$3,500.00300$3,437.53
Guardrail end treatment- parallel approach terminal, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Guardrail end treatment- parallel approach terminal, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 333$3,500.00122$3,500.00
District 422$3,430.00117$3,390.63
District 230$3,453.05112$3,311.44
District 516$3,659.0087$3,510.00
District 715$3,500.0078$3,529.89
District 610$3,735.0065$3,564.00
District 115$3,515.0062$3,517.34
Guardrail end treatment- parallel approach terminal, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Guardrail end treatment- parallel approach terminal, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 235$3,600.00
2 to 335$3,505.16
3 to 635$3,515.00
6 to 3636$3,400.00
Guardrail end treatment- parallel approach terminal, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Guardrail end treatment- parallel approach terminal
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1937District 110$3,764.69$3,807.354AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T2A73District 24$2,571.00$2,776.028C.W. ROBERTS CONTRACTING, INC.FDOT
28 OCT 2026T2A86District 21$2,848.50$3,400.008PIGOTT ASPHALT AND SITEWORK LLCFDOT
28 OCT 2026T2B08District 21$4,701.20$4,701.201ANDERSON COLUMBIA CO., INC.FDOT
28 OCT 2026T3970District 32$5,300.00$3,200.005RBM CONTRACTING SERVICES, LLCFDOT
28 OCT 2026T3A21District 34$3,717.30$3,717.303ANDERSON COLUMBIA CO., INC.FDOT
28 OCT 2026T4765District 41$3,819.29$3,909.646GENERAL ASPHALT COMPANY, LLCFDOT
28 OCT 2026T5914District 53$3,558.00$3,650.003MASCI GENERAL CONTRACTORS, INCFDOT
28 OCT 2026T7591District 733$3,315.74$3,402.285PREFERRED MATERIALS INC.FDOT
30 SEP 2026T2A79District 26$4,746.12$4,746.121ANDERSON COLUMBIA CO., INC.FDOT
30 SEP 2026T2A80District 24$6,400.13$3,640.003ANDERSON COLUMBIA CO., INC.FDOT
30 SEP 2026T3908District 34$5,400.00$3,977.115RBM CONTRACTING SERVICES, LLCFDOT
30 SEP 2026T3937District 34$3,500.00$3,750.004MURPHREE BRIDGE CORPORATIONFDOT
30 SEP 2026T6398District 66$3,061.25$3,041.124OHLA USA INCFDOT
30 SEP 2026T6593District 62$4,221.42$3,460.005OHLA USA INCFDOT
Latest FDOT contracts carrying Guardrail end treatment- parallel approach terminal

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way