Guardrail transition to rigid barrier, f&i- index 536- 001, trailing unit price, Florida

Low bidders on FDOT contracts carried a median of $1,801.96 per EACH for item 0536-8113, guardrail transition to rigid barrier, f&i- index 536- 001, trailing, over the 24 months to 28 OCT 2026, across 20 low bids. Half of all 101 bids fell between $1,400.00 and $2,200.00.

Owner
Florida DOT
Item
0536-8113
Unit
EACH
Latest letting
28 OCT 2026
$1,801.96Low bidder's median, per EACH
$1,800.00Median of all bids, per EACH
20Contracts in the window

By year of letting

Guardrail transition to rigid barrier, f&i- index 536- 001, trailing, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202188$2,137.5444$1,442.50
202299$1,660.0025$1,660.00
20231111$1,800.0038$1,721.38
202498$1,655.0035$1,808.30
202588$1,547.5044$1,445.91
20261111$2,000.0052$1,943.62
Guardrail transition to rigid barrier, f&i- index 536- 001, trailing, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Guardrail transition to rigid barrier, f&i- index 536- 001, trailing, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 45$1,595.0028$1,480.00
District 14$1,801.9619$1,845.00
District 53$1,500.0017$1,500.00
District 35$2,800.0017$2,800.00
Guardrail transition to rigid barrier, f&i- index 536- 001, trailing, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Guardrail transition to rigid barrier, f&i- index 536- 001, trailing, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 25$1,748.00
2 to 25$2,200.00
2 to 45$2,800.00
4 to 105$1,299.01
Guardrail transition to rigid barrier, f&i- index 536- 001, trailing, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Guardrail transition to rigid barrier, f&i- index 536- 001, trailing
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1937District 11$1,803.92$1,824.464AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T2A73District 21$1,748.00$1,775.008C.W. ROBERTS CONTRACTING, INC.FDOT
28 OCT 2026T3970District 32$4,565.00$2,600.005RBM CONTRACTING SERVICES, LLCFDOT
30 SEP 2026T6398District 63$1,720.50$1,769.204OHLA USA INCFDOT
29 JUL 2026T1939District 12$2,000.00$1,981.004OHLA USA INCFDOT
10 JUN 2026T3952District 32$3,045.05$2,397.532RJ GORMAN CONTRACTING LLCFDOT
31 MAR 2026T3845District 31$2,800.00$2,850.004PHOENIX CONSTRUCTION SERVICES, INC.FDOT
25 MAR 2026T1920District 12$1,800.00$1,925.016SEMA CONSTRUCTION, INC.FDOT
25 MAR 2026T5876District 55$1,294.99$1,307.996TIMOTHY ROSE CONTRACTING, INC.FDOT
28 JAN 2026T3954District 32$2,200.00$2,200.003MURPHREE BRIDGE CORPORATIONFDOT
28 JAN 2026T5875District 52$2,150.00$2,050.006C.W. ROBERTS CONTRACTING, INC.FDOT
03 DEC 2025T4729District 43$2,850.00$3,200.008WEBBER, LLCFDOT
24 SEP 2025T2A24District 26$1,245.00$1,232.508MASTEC CIVIL LLCFDOT
27 AUG 2025T4688District 410$1,299.01$1,298.997CENTRAL CIVIL CONSTRUCTION CO.FDOT
30 JUL 2025T4674District 42$1,595.00$1,344.504GENERAL ASPHALT COMPANY, LLCFDOT
Latest FDOT contracts carrying Guardrail transition to rigid barrier, f&i- index 536- 001, trailing

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy