Guardrail removal unit price, Florida

Low bidders on FDOT contracts carried a median of $2.83 per LF for item 0536-73, guardrail removal, over the 24 months to 28 OCT 2026, across 138 low bids. Half of all 634 bids fell between $2.15 and $4.66.

Owner
Florida DOT
Item
0536-73
Unit
LF
Latest letting
28 OCT 2026
$2.83Low bidder's median, per LF
$2.63Median of all bids, per LF
139Contracts in the window

By year of letting

Guardrail removal, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20186464$3.18310$3.32
20196565$3.00291$3.20
20205050$2.23258$2.32
20216767$2.50336$2.48
20227070$3.39250$3.00
20238080$3.26269$3.23
20247474$3.00282$3.00
20256060$3.25275$2.85
20266564$2.50313$2.40
Guardrail removal, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Guardrail removal, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 334$3.38125$3.28
District 230$2.94111$2.50
District 419$2.4598$2.44
District 516$2.6085$2.65
District 714$2.9275$3.00
District 611$2.8173$3.00
District 114$2.3767$2.38
Guardrail removal, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Guardrail removal, FDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
15 to 22634$3.96
231 to 57635$3.12
610 to 1,95234$3.03
1,960 to 19,69635$2.11
Guardrail removal, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Guardrail removal
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1937District 14,544$2.36$2.384AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T2A73District 24,402$2.30$2.398C.W. ROBERTS CONTRACTING, INC.FDOT
28 OCT 2026T2A86District 22,184$2.37$2.208PIGOTT ASPHALT AND SITEWORK LLCFDOT
28 OCT 2026T2B08District 2112$2.69$2.691ANDERSON COLUMBIA CO., INC.FDOT
28 OCT 2026T3970District 31,104$6.00$2.255RBM CONTRACTING SERVICES, LLCFDOT
28 OCT 2026T3A21District 3266$2.12$2.123ANDERSON COLUMBIA CO., INC.FDOT
28 OCT 2026T4765District 472$5.84$5.256GENERAL ASPHALT COMPANY, LLCFDOT
28 OCT 2026T5914District 5495$5.00$2.003MASCI GENERAL CONTRACTORS, INCFDOT
28 OCT 2026T7591District 72,736$2.07$2.225PREFERRED MATERIALS INC.FDOT
30 SEP 2026T1944District 1220$3.73$17.368ZEP CONSTRUCTION, INC.FDOT
30 SEP 2026T2A79District 2452$2.88$2.881ANDERSON COLUMBIA CO., INC.FDOT
30 SEP 2026T2A80District 21,217$2.17$2.173ANDERSON COLUMBIA CO., INC.FDOT
30 SEP 2026T3908District 3276$4.00$4.005RBM CONTRACTING SERVICES, LLCFDOT
30 SEP 2026T3937District 31,859$2.00$2.754MURPHREE BRIDGE CORPORATIONFDOT
30 SEP 2026T5893District 51,885$2.50$2.758MASCI GENERAL CONTRACTORS, INCFDOT
Latest FDOT contracts carrying Guardrail removal

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy