Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3 unit price, Florida

Low bidders on FDOT contracts carried a median of $3,450.00 per EACH for item 0536-8112, guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3, over the 24 months to 28 OCT 2026, across 39 low bids. Half of all 186 bids fell between $3,097.67 and $3,951.96.

Owner
Florida DOT
Item
0536-8112
Unit
EACH
Latest letting
28 OCT 2026
$3,450.00Low bidder's median, per EACH
$3,500.00Median of all bids, per EACH
39Contracts in the window

By year of letting

Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20212020$3,035.75100$3,173.18
20221717$4,151.2759$4,000.00
20232828$3,695.7883$3,844.72
20241817$3,725.0078$3,512.50
20252121$3,280.00109$3,325.00
20261515$3,650.0065$3,600.00
Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 48$3,136.5145$3,170.00
District 29$3,375.0041$3,375.00
District 38$3,827.6630$3,500.00
District 17$3,301.5929$3,598.70
District 54$3,880.0023$3,600.00
District 63$3,287.8818$3,674.25
Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 19$3,287.88
1 to 310$3,483.85
3 to 610$3,725.00
6 to 1910$3,365.00
Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1937District 11$3,816.98$3,860.994AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T2A73District 21$3,779.00$3,797.528C.W. ROBERTS CONTRACTING, INC.FDOT
30 SEP 2026T3937District 34$3,650.00$3,925.004MURPHREE BRIDGE CORPORATIONFDOT
29 JUL 2026T1939District 12$2,000.00$3,938.404OHLA USA INCFDOT
10 JUN 2026T3981District 34$3,800.00$3,800.003ANDERSON COLUMBIA CO., INC.FDOT
20 MAY 2026T2A68District 28$3,550.00$3,787.504ANDERSON COLUMBIA CO., INC.FDOT
29 APR 2026T2809District 23$3,375.00$3,375.003ANDERSON COLUMBIA CO., INC.FDOT
25 MAR 2026T1919District 16$4,286.11$3,634.354AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
25 MAR 2026T3939District 34$4,974.63$3,500.003RJ GORMAN CONTRACTING LLCFDOT
25 MAR 2026T3951District 38$3,855.33$3,073.944RJ GORMAN CONTRACTING LLCFDOT
25 FEB 2026T2A58District 24$2,603.55$2,852.923PREFERRED MATERIALS INC.FDOT
28 JAN 2026T2A54District 21$3,000.00$3,041.235PREFERRED MATERIALS INC.FDOT
28 JAN 2026T3929District 34$4,000.00$3,858.137ANDERSON COLUMBIA CO., INC.FDOT
28 JAN 2026T3988District 316$3,186.78$3,300.003ANDERSON COLUMBIA CO., INC.FDOT
28 JAN 2026T5875District 54$3,500.00$3,475.006C.W. ROBERTS CONTRACTING, INC.FDOT
Latest FDOT contracts carrying Guardrail transition to rigid barrier, f&i- index 536- 001, approach tl-3

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy