Its cabinet- remove unit price, Florida
Low bidders on FDOT contracts carried a median of $1,000.75 per EACH for item 0676-2600, its cabinet- remove, over the 24 months to 28 OCT 2026, across 8 low bids. Half of all 38 bids fell between $796.25 and $1,755.00.
- Owner
- Florida DOT
- Item
- 0676-2600
- Unit
- EACH
- Latest letting
- 30 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 4 | 4 | $724.30 | 16 | $798.50 |
| 2020 | 2 | 2 | $928.30 | 8 | $597.39 |
| 2021 | 9 | 9 | $526.68 | 40 | $600.00 |
| 2022 | 5 | 5 | $650.00 | 21 | $1,209.00 |
| 2023 | 9 | 9 | $721.00 | 37 | $1,000.00 |
| 2024 | 10 | 10 | $870.50 | 39 | $1,000.00 |
| 2025 | 4 | 4 | $1,168.86 | 19 | $1,500.00 |
| 2026 | 3 | 3 | $780.00 | 16 | $823.76 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 SEP 2026 | T6398 | District 6 | 1 | $765.50 | $797.50 | 4 | OHLA USA INC | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 1 | $780.00 | $815.00 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T5876 | District 5 | 1 | $961.79 | $918.00 | 6 | TIMOTHY ROSE CONTRACTING, INC. | FDOT |
| 30 APR 2025 | T5793 | District 5 | 1 | $2,100.00 | $2,000.00 | 7 | P & S PAVING, INC. | FDOT |
| 26 MAR 2025 | T4710 | District 4 | 1 | $550.00 | $550.00 | 2 | OHLA USA INC | FDOT |
| 29 JAN 2025 | T4705 | District 4 | 3 | $1,298.00 | $1,430.00 | 5 | GLF POSILLICO JV | FDOT |
| 29 JAN 2025 | T5845 | District 5 | 1 | $1,039.71 | $1,039.71 | 5 | SICE INC | FDOT |
| 30 OCT 2024 | T7517 | District 7 | 2 | $1,883.61 | $1,620.00 | 3 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 28 AUG 2024 | T6597 | District 6 | 1 | $850.00 | $1,044.95 | 4 | FLORIDA SIGNAL & LIGHTING CONTRACTORS, INC. | FDOT |
| 14 AUG 2024 | T1899 | District 1 | 4 | $685.00 | $685.08 | 4 | LANE CONSTRUCTION CORPORATION (THE) | FDOT |
| 19 JUN 2024 | T7501 | District 7 | 1 | $1,000.00 | $795.00 | 4 | WEBBER, LLC | FDOT |
| 22 MAY 2024 | T4655 | District 4 | 1 | $1,000.00 | $1,500.00 | 4 | OHLA USA INC | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 6 | $891.00 | $903.00 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
| 28 FEB 2024 | T5822 | District 5 | 1 | $1,800.00 | $1,735.00 | 4 | P & S PAVING, INC. | FDOT |
| 28 FEB 2024 | T6557 | District 6 | 1 | $850.00 | $1,100.00 | 5 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A B | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way