Its cabinet, furnish & install, pole mount with sunshield, 24" w x 46" h x 22" d unit price, Florida
Low bidders on FDOT contracts carried a median of $9,624.91 per EACH for item 0676-2122, its cabinet, furnish & install, pole mount with sunshield, 24" w x 46" h x 22" d, over the 24 months to 28 OCT 2026, across 20 low bids. Half of all 104 bids fell between $9,315.71 and $12,141.
- Owner
- Florida DOT
- Item
- 0676-2122
- Unit
- EACH
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $5,776.52 | 45 | $7,475.74 |
| 2019 | 2 | 2 | $8,521.82 | 11 | $6,000.00 |
| 2020 | 6 | 6 | $6,250.03 | 33 | $7,000.00 |
| 2021 | 17 | 17 | $7,000.00 | 79 | $7,200.00 |
| 2022 | 20 | 20 | $9,300.00 | 72 | $8,737.90 |
| 2023 | 15 | 15 | $9,173.55 | 56 | $9,616.42 |
| 2024 | 5 | 5 | $8,826.29 | 17 | $9,530.00 |
| 2025 | 13 | 13 | $8,970.00 | 67 | $10,300 |
| 2026 | 6 | 6 | $11,640 | 34 | $11,703 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 4 | 6 | $9,482.50 | 38 | $10,740 |
| District 5 | 5 | $11,580 | 26 | $10,731 |
| District 1 | 3 | $10,900 | 14 | $11,225 |
| District 7 | 3 | $8,084.25 | 12 | $9,268.15 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 5 | $9,465.00 |
| 2 to 2 | 5 | $10,061 |
| 3 to 4 | 5 | $9,500.00 |
| 5 to 16 | 5 | $10,300 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T3A25 | District 3 | 1 | $9,749.82 | $9,900.00 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 10 JUN 2026 | T5884 | District 5 | 6 | $11,580 | $9,537.50 | 6 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 20 MAY 2026 | T4666 | District 4 | 2 | $10,061 | $12,864 | 8 | OHLA USA INC | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 2 | $11,700 | $12,100 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T5876 | District 5 | 2 | $12,171 | $12,191 | 6 | TIMOTHY ROSE CONTRACTING, INC. | FDOT |
| 25 FEB 2026 | T4739 | District 4 | 3 | $11,800 | $11,800 | 5 | RANGER CONSTRUCTION INDUSTRIES, INC. | FDOT |
| 03 DEC 2025 | T4717 | District 4 | 4 | $8,900.00 | $10,018 | 8 | RTECH ENGINEERING, LLC | FDOT |
| 24 SEP 2025 | T2A24 | District 2 | 7 | $10,300 | $10,494 | 8 | MASTEC CIVIL LLC | FDOT |
| 27 AUG 2025 | T4688 | District 4 | 1 | $8,897.21 | $8,897.21 | 7 | CENTRAL CIVIL CONSTRUCTION CO. | FDOT |
| 30 JUL 2025 | T5871 | District 5 | 1 | $14,271 | $12,715 | 2 | CARR CONSTRUCTION, LLC | FDOT |
| 30 JUL 2025 | T7574 | District 7 | 16 | $8,084.25 | $10,668 | 6 | TRAFFIC MANAGEMENT SOLUTIONS, LLC | FDOT |
| 28 MAY 2025 | T1926 | District 1 | 5 | $10,900 | $10,300 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 30 APR 2025 | T5793 | District 5 | 3 | $11,500 | $10,780 | 7 | P & S PAVING, INC. | FDOT |
| 26 FEB 2025 | T4691 | District 4 | 3 | $9,500.00 | $15,500 | 5 | MASTEC CIVIL LLC | FDOT |
| 29 JAN 2025 | T1907 | District 1 | 2 | $7,000.00 | $9,710.00 | 3 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.