Light pole complete, furnish & install standard pole foundation, 35' mounting height unit price, Florida

Low bidders on FDOT contracts carried a median of $5,650.00 per EACH for item 0715-4-12, light pole complete, furnish & install standard pole foundation, 35' mounting height, from 31 JAN 2018 to 15 JUN 2022, across 73 low bids. Half of all 362 bids fell between $5,200.00 and $6,699.68.

Owner
Florida DOT
Item
0715-4-12
Unit
EACH
Latest letting
15 JUN 2022
$5,650.00Low bidder's median, per EACH
$5,800.08Median of all bids, per EACH
73Contracts in the window

By year of letting

Light pole complete, furnish & install standard pole foundation, 35' mounting height, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20182121$5,522.70104$5,569.39
20191818$5,450.3086$5,918.72
20201212$5,583.2264$5,970.00
20211414$5,820.0071$5,880.00
202288$7,579.5037$6,772.50
Light pole complete, furnish & install standard pole foundation, 35' mounting height, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Light pole complete, furnish & install standard pole foundation, 35' mounting height, FDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 120$5,357.66100$5,687.16
District 613$5,500.0073$5,650.00
District 713$5,800.1667$6,000.00
District 412$5,337.3265$5,800.00
District 59$6,000.0040$6,000.00
District 25$6,770.0514$6,724.02
Light pole complete, furnish & install standard pole foundation, 35' mounting height, FDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Light pole complete, furnish & install standard pole foundation, 35' mounting height, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 218$5,556.75
2 to 418$5,875.21
4 to 818$5,603.73
9 to 3519$5,578.55
Light pole complete, furnish & install standard pole foundation, 35' mounting height, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Light pole complete, furnish & install standard pole foundation, 35' mounting height
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
15 JUN 2022T3671District 39$9,315.00$9,263.003M OF TALLAHASSEE, INC.FDOT
15 JUN 2022T7476District 74$5,100.00$5,100.003JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANYFDOT
25 MAY 2022T2843District 24$10,050$6,496.704P & S PAVING, INC.FDOT
25 MAY 2022T7496District 74$8,544.14$8,544.143PREFERRED MATERIALS INC.FDOT
27 APR 2022T2823District 26$6,450.00$6,503.994SUPERIOR CONSTRUCTION COMPANY SOUTHEAST, LLCFDOT
30 MAR 2022T4607District 49$7,359.00$7,359.007FLORIDA ENGINEERING & DEVELOPMENT CORPFDOT
23 FEB 2022T1844District 111$7,800.00$7,642.006PRINCE CONTRACTING, LLC.FDOT
12 JAN 2022T4583District 414$6,715.00$6,656.327VECELLIO & GROGAN, INC.FDOT
27 OCT 2021T1839District 15$5,760.00$8,000.003TRAFFIC CONTROL DEVICES, INC.FDOT
29 SEP 2021T6461District 62$5,400.00$6,065.0010HORIZON CONTRACTORS, INC.FDOT
29 SEP 2021T6527District 66$5,000.00$5,694.207FLORIDA SIGNAL & LIGHTING CONTRACTORS, INC.FDOT
25 AUG 2021T5728District 525$6,472.77$5,904.773SOUTHLAND CONSTRUCTION, INC.FDOT
28 JUL 2021T1822District 14$5,650.00$6,400.004WIRETEK SOLUTIONS LLCFDOT
28 JUL 2021T4569District 42$5,370.00$6,400.005WEEKLEY ASPHALT PAVING, INC.FDOT
26 MAY 2021T2810District 22$7,264.00$6,628.712KIEWIT INFRASTRUCTURE SOUTH CO.FDOT
Latest FDOT contracts carrying Light pole complete, furnish & install standard pole foundation, 35' mounting height

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy