Light pole complete, furnish & install standard pole foundation, 45' mounting height unit price, Florida
Low bidders on FDOT contracts carried a median of $6,426.74 per EACH for item 0715-4-14, light pole complete, furnish & install standard pole foundation, 45' mounting height, from 28 FEB 2018 to 27 APR 2022, across 86 low bids. Half of all 420 bids fell between $5,898.38 and $7,519.00.
- Owner
- Florida DOT
- Item
- 0715-4-14
- Unit
- EACH
- Latest letting
- 27 APR 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 24 | 24 | $6,460.64 | 117 | $6,375.23 |
| 2019 | 25 | 25 | $6,627.00 | 108 | $6,986.76 |
| 2020 | 15 | 15 | $6,200.00 | 77 | $6,100.00 |
| 2021 | 19 | 19 | $6,108.95 | 105 | $6,380.00 |
| 2022 | 3 | 3 | $9,000.00 | 13 | $8,494.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 6 | 23 | $6,717.53 | 126 | $6,194.00 |
| District 4 | 18 | $6,000.00 | 89 | $6,426.51 |
| District 7 | 15 | $6,278.71 | 82 | $6,329.80 |
| District 1 | 15 | $7,000.00 | 68 | $7,475.00 |
| District 5 | 9 | $6,271.86 | 35 | $6,800.00 |
| District 2 | 4 | $7,696.06 | 15 | $7,843.88 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 21 | $6,787.00 |
| 3 to 8 | 22 | $6,438.02 |
| 9 to 18 | 21 | $6,278.71 |
| 18 to 487 | 22 | $5,827.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 27 APR 2022 | T2823 | District 2 | 3 | $8,100.00 | $8,100.00 | 4 | SUPERIOR CONSTRUCTION COMPANY SOUTHEAST, LLC | FDOT |
| 30 MAR 2022 | T1842 | District 1 | 2 | $12,913 | $12,084 | 4 | PREFERRED MATERIALS INC. | FDOT |
| 26 JAN 2022 | T6519 | District 6 | 2 | $9,000.00 | $8,009.28 | 5 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A BC&E | FDOT |
| 08 DEC 2021 | T6518 | District 6 | 4 | $6,806.48 | $7,354.85 | 8 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
| 27 OCT 2021 | T1839 | District 1 | 2 | $6,963.00 | $9,400.00 | 3 | TRAFFIC CONTROL DEVICES, INC. | FDOT |
| 27 OCT 2021 | T6511 | District 6 | 18 | $10,000 | $10,000 | 5 | PRINCE CONTRACTING, LLC. | FDOT |
| 29 SEP 2021 | T4586 | District 4 | 1 | $4,187.30 | $4,187.30 | 1 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
| 25 AUG 2021 | T4585 | District 4 | 9 | $5,920.00 | $7,190.00 | 5 | RANGER CONSTRUCTION INDUSTRIES, INC. | FDOT |
| 25 AUG 2021 | T5728 | District 5 | 33 | $7,532.90 | $6,871.01 | 3 | SOUTHLAND CONSTRUCTION, INC. | FDOT |
| 28 JUL 2021 | T4574 | District 4 | 11 | $6,000.00 | $6,000.00 | 6 | ARC ELECTRIC INC | FDOT |
| 28 JUL 2021 | T6508 | District 6 | 254 | $5,600.00 | $5,650.00 | 7 | HALLEY ENGINEERING CONTRACTORS, INC. | FDOT |
| 28 APR 2021 | T1797 | District 1 | 11 | $7,250.00 | $6,625.00 | 4 | HORSEPOWER ELECTRIC, INC. | FDOT |
| 28 APR 2021 | T7474 | District 7 | 13 | $5,950.00 | $6,125.00 | 6 | HIGHWAY SAFETY DEVICES, INC. | FDOT |
| 31 MAR 2021 | T1783 | District 1 | 46 | $5,700.00 | $6,141.47 | 7 | SACYR CONSTRUCCION SA | FDOT |
| 31 MAR 2021 | T1795 | District 1 | 1 | $6,813.56 | $6,813.56 | 3 | CHINCHOR ELECTRIC INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.