Light pole complete, remove pole and foundation unit price, Florida
Low bidders on FDOT contracts carried a median of $700.00 per EACH for item 0715-4-70, light pole complete, remove pole and foundation, from 31 JAN 2018 to 15 JUN 2022, across 154 low bids. Half of all 764 bids fell between $525.50 and $1,060.00.
- Owner
- Florida DOT
- Item
- 0715-4-70
- Unit
- EACH
- Latest letting
- 15 JUN 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 41 | 41 | $650.00 | 218 | $692.77 |
| 2019 | 36 | 36 | $615.60 | 153 | $669.48 |
| 2020 | 19 | 19 | $610.17 | 116 | $629.00 |
| 2021 | 35 | 35 | $630.00 | 177 | $650.00 |
| 2022 | 23 | 23 | $1,000.00 | 100 | $1,000.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 6 | 36 | $715.00 | 205 | $730.00 |
| District 4 | 34 | $614.92 | 194 | $619.67 |
| District 1 | 31 | $700.00 | 147 | $744.45 |
| District 7 | 15 | $650.00 | 74 | $655.00 |
| District 5 | 19 | $850.00 | 72 | $885.00 |
| District 2 | 12 | $750.00 | 53 | $644.70 |
| District 3 | 5 | $980.00 | 14 | $1,220.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 38 | $675.00 |
| 2 to 5 | 39 | $900.00 |
| 5 to 17 | 38 | $622.17 |
| 17 to 209 | 39 | $660.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 JUN 2022 | T3671 | District 3 | 17 | $1,437.50 | $1,429.00 | 3 | M OF TALLAHASSEE, INC. | FDOT |
| 15 JUN 2022 | T5724 | District 5 | 75 | $900.00 | $1,060.00 | 5 | SUPERIOR CONSTRUCTION COMPANY SOUTHEAST, LLC | FDOT |
| 15 JUN 2022 | T7476 | District 7 | 96 | $650.00 | $650.00 | 3 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY | FDOT |
| 25 MAY 2022 | T4605 | District 4 | 6 | $1,874.10 | $1,191.00 | 3 | ZAHLENE ENTERPRISES INC. | FDOT |
| 25 MAY 2022 | T5747 | District 5 | 11 | $1,189.34 | $1,011.82 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 25 MAY 2022 | T6538 | District 6 | 1 | $1,610.00 | $1,614.13 | 6 | LEAD ENGINEERING CONTRACTORS, LLC | FDOT |
| 25 MAY 2022 | T7496 | District 7 | 3 | $1,449.22 | $1,449.22 | 3 | PREFERRED MATERIALS INC. | FDOT |
| 25 MAY 2022 | T7498 | District 7 | 3 | $982.24 | $890.28 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 25 MAY 2022 | T4606 | District 4 | 17 | $950.00 | $975.00 | 6 | STRONGCORE GROUP, LLC | FDOT |
| 27 APR 2022 | T1787 | District 1 | 16 | $955.00 | $1,055.00 | 4 | RUSSELL ENGINEERING, INC. | FDOT |
| 27 APR 2022 | T2823 | District 2 | 3 | $900.00 | $900.50 | 4 | SUPERIOR CONSTRUCTION COMPANY SOUTHEAST, LLC | FDOT |
| 27 APR 2022 | T6514 | District 6 | 2 | $1,272.00 | $1,462.92 | 3 | ASPHALT GROUP, INC. | FDOT |
| 30 MAR 2022 | T9029 | StateWide | 88 | $1,500.00 | $1,311.00 | 2 | INGRAM SIGNALIZATION, INC. | FDOT |
| 23 FEB 2022 | T1801 | District 1 | 2 | $755.00 | $810.00 | 5 | RUSSELL ENGINEERING, INC. | FDOT |
| 23 FEB 2022 | T1844 | District 1 | 3 | $1,010.00 | $1,005.00 | 6 | PRINCE CONTRACTING, LLC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.