Lighting conductors, f&i, insulated, no.8 - 6 unit price, Florida
Low bidders on FDOT contracts carried a median of $3.05 per LF for item 0715-1-12, lighting conductors, f&i, insulated, no.8 - 6, over the 24 months to 28 OCT 2026, across 146 low bids. Half of all 769 bids fell between $2.64 and $3.81.
- Owner
- Florida DOT
- Item
- 0715-1-12
- Unit
- LF
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 71 | 73 | $1.50 | 406 | $1.50 |
| 2019 | 72 | 76 | $1.50 | 337 | $1.55 |
| 2020 | 46 | 46 | $1.50 | 270 | $1.60 |
| 2021 | 67 | 70 | $2.00 | 373 | $2.01 |
| 2022 | 66 | 70 | $2.75 | 273 | $2.85 |
| 2023 | 73 | 77 | $3.40 | 296 | $3.60 |
| 2024 | 72 | 72 | $3.45 | 257 | $3.50 |
| 2025 | 71 | 72 | $3.00 | 376 | $3.20 |
| 2026 | 56 | 58 | $3.05 | 344 | $3.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 4 | 42 | $3.39 | 252 | $3.20 |
| District 6 | 24 | $3.43 | 153 | $3.36 |
| District 7 | 18 | $2.78 | 100 | $2.90 |
| District 1 | 24 | $2.80 | 91 | $2.80 |
| District 5 | 16 | $2.46 | 80 | $2.67 |
| District 3 | 12 | $4.30 | 46 | $4.72 |
| District 2 | 8 | $2.85 | 41 | $3.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 126 to 1,770 | 36 | $3.63 |
| 1,793 to 3,388 | 37 | $3.37 |
| 3,468 to 10,435 | 36 | $3.12 |
| 10,683 to 390,148 | 37 | $2.64 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T1941 | District 1 | 3,388 | $3.54 | $3.33 | 2 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 28 OCT 2026 | T1947 | District 1 | 15,641 | $3.20 | $3.23 | 4 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 28 OCT 2026 | T4765 | District 4 | 13,356 | $4.28 | $3.75 | 6 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 28 OCT 2026 | T5914 | District 5 | 23,165 | $2.85 | $2.40 | 3 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 28 OCT 2026 | T7616 | District 7 | 372 | $2.16 | $2.28 | 5 | CHINCHOR ELECTRIC INC. | FDOT |
| 30 SEP 2026 | T5893 | District 5 | 2,101 | $3.38 | $3.49 | 8 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 30 SEP 2026 | T6398 | District 6 | 16,634 | $3.00 | $3.20 | 4 | OHLA USA INC | FDOT |
| 30 SEP 2026 | T6593 | District 6 | 1,962 | $2.81 | $3.75 | 5 | OHLA USA INC | FDOT |
| 30 SEP 2026 | T6613 | District 6 | 2,150 | $5.00 | $3.50 | 9 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
| 26 AUG 2026 | T1940 | District 1 | 1,294 | $2.85 | $2.58 | 4 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 26 AUG 2026 | T4757 | District 4 | 61,946 | $1.83 | $2.83 | 12 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. | FDOT |
| 26 AUG 2026 | T4764 | District 4 | 5,658 | $2.73 | $2.91 | 9 | OHLA USA INC | FDOT |
| 26 AUG 2026 | T4773 | District 4 | 42,034 | $2.40 | $2.80 | 13 | GERELCO TRAFFIC CONTROLS, INC. | FDOT |
| 26 AUG 2026 | T7624 | District 7 | 126 | $1.91 | $4.17 | 5 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. | FDOT |
| 29 JUL 2026 | T4745 | District 4 | 14,049 | $2.86 | $2.87 | 6 | FLORIDA ENGINEERING & DEVELOPMENT CORP | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way