Lighting conductors, f&i, insulated, no. 10 or < unit price, Florida
Low bidders on FDOT contracts carried a median of $1.66 per LF for item 0715-1-11, lighting conductors, f&i, insulated, no. 10 or <, over the 24 months to 28 OCT 2026, across 12 low bids. Half of all 58 bids fell between $1.48 and $3.40.
- Owner
- Florida DOT
- Item
- 0715-1-11
- Unit
- LF
- Latest letting
- 30 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 11 | 11 | $0.75 | 57 | $0.75 |
| 2019 | 8 | 8 | $1.29 | 30 | $1.58 |
| 2020 | 5 | 5 | $1.30 | 29 | $1.15 |
| 2021 | 5 | 5 | $1.25 | 29 | $1.30 |
| 2022 | 8 | 8 | $1.68 | 37 | $1.75 |
| 2023 | 3 | 3 | $1.30 | 11 | $1.70 |
| 2024 | 7 | 7 | $2.05 | 30 | $2.57 |
| 2025 | 6 | 6 | $1.51 | 30 | $1.99 |
| 2026 | 5 | 5 | $2.10 | 25 | $1.90 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 54 to 96 | 3 | $1.55 |
| 198 to 378 | 3 | $3.75 |
| 592 to 1,800 | 3 | $1.76 |
| 2,400 to 9,028 | 3 | $1.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 SEP 2026 | T3A26 | District 3 | 302 | $2.10 | $3.06 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 20 MAY 2026 | T5863 | District 5 | 96 | $1.55 | $2.55 | 6 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 20 MAY 2026 | T7607 | District 7 | 378 | $10.29 | $1.38 | 6 | BLACKTIP SERVICES INCORPORATED | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 9,028 | $1.10 | $1.11 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 28 JAN 2026 | T3988 | District 3 | 54 | $5.31 | $5.31 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 03 DEC 2025 | T2A53 | District 2 | 592 | $1.25 | $1.96 | 8 | VECELLIO & GROGAN, INC. | FDOT |
| 24 SEP 2025 | T7592 | District 7 | 96 | $1.40 | $2.84 | 6 | CONE & GRAHAM, INC. | FDOT |
| 30 JUL 2025 | T4674 | District 4 | 1,800 | $1.76 | $1.87 | 4 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 28 MAY 2025 | T1926 | District 1 | 4,508 | $1.52 | $1.70 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 26 FEB 2025 | T4697 | District 4 | 2,400 | $1.50 | $2.00 | 4 | OHLA USA INC | FDOT |
| 29 JAN 2025 | T3949 | District 3 | 1,044 | $4.75 | $4.75 | 3 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 13 NOV 2024 | T3916 | District 3 | 198 | $3.75 | $3.75 | 3 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 25 SEP 2024 | T2987 | District 2 | 4,295 | $1.90 | $1.45 | 4 | DE MOYA ASPHALT JOINT VENTURE | FDOT |
| 28 AUG 2024 | T4682 | District 4 | 46 | $2.05 | $3.00 | 7 | OHLA USA INC | FDOT |
| 14 AUG 2024 | T1899 | District 1 | 1,017 | $0.90 | $0.91 | 4 | LANE CONSTRUCTION CORPORATION (THE) | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way