Manholes, j-7, >10' unit price, Florida
Low bidders on FDOT contracts carried a median of $20,000 per EACH for item 0425-2-72, manholes, j-7, >10', over the 24 months to 28 OCT 2026, across 10 low bids. Half of all 56 bids fell between $14,426 and $28,371.
- Owner
- Florida DOT
- Item
- 0425-2-72
- Unit
- EACH
- Latest letting
- 30 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 6 | 6 | $8,650.00 | 34 | $9,135.00 |
| 2019 | 6 | 6 | $9,725.50 | 27 | $10,664 |
| 2020 | 3 | 3 | $7,489.00 | 28 | $7,132.04 |
| 2021 | 6 | 6 | $9,912.50 | 30 | $8,461.06 |
| 2022 | 8 | 8 | $17,549 | 35 | $16,100 |
| 2023 | 7 | 7 | $22,000 | 36 | $21,625 |
| 2024 | 8 | 8 | $12,250 | 31 | $15,665 |
| 2025 | 5 | 5 | $16,692 | 24 | $14,851 |
| 2026 | 5 | 5 | $21,000 | 32 | $21,378 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 SEP 2026 | T6398 | District 6 | 53 | $17,171 | $23,985 | 4 | OHLA USA INC | FDOT |
| 10 JUN 2026 | T5888 | District 5 | 6 | $37,700 | $24,009 | 8 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 20 MAY 2026 | T4666 | District 4 | 5 | $21,000 | $17,100 | 8 | OHLA USA INC | FDOT |
| 29 APR 2026 | T7562 | District 7 | 2 | $19,000 | $23,800 | 7 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T2A62 | District 2 | 3 | $23,700 | $23,700 | 5 | MAER HOMES, LLC | FDOT |
| 27 AUG 2025 | T4688 | District 4 | 15 | $14,241 | $13,200 | 7 | CENTRAL CIVIL CONSTRUCTION CO. | FDOT |
| 11 JUN 2025 | T1904 | District 1 | 1 | $16,692 | $15,649 | 2 | RUSSELL ENGINEERING, INC. | FDOT |
| 28 MAY 2025 | T4575 | District 4 | 1 | $28,162 | $44,081 | 4 | ROADWAY CONSTRUCTION, LLC | FDOT |
| 26 FEB 2025 | T6602 | District 6 | 1 | $7,200.00 | $12,200 | 7 | HORIZON CONTRACTORS, INC. | FDOT |
| 29 JAN 2025 | T4713 | District 4 | 1 | $31,059 | $28,030 | 4 | SIGNAL TECHNOLOGY AND INSTALLATION CORP. | FDOT |
| 25 SEP 2024 | T4681 | District 4 | 11 | $26,200 | $26,200 | 1 | MASTEC CIVIL LLC | FDOT |
| 14 AUG 2024 | T1899 | District 1 | 1 | $111,000 | $115,500 | 4 | LANE CONSTRUCTION CORPORATION (THE) | FDOT |
| 31 JUL 2024 | T4684 | District 4 | 2 | $9,702.94 | $13,920 | 5 | FLORIDA ENGINEERING & DEVELOPMENT CORP | FDOT |
| 22 MAY 2024 | T4655 | District 4 | 2 | $17,000 | $18,500 | 4 | OHLA USA INC | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 7 | $13,500 | $18,750 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.