Manholes, j-8, partial unit price, Florida

Low bidders on FDOT contracts carried a median of $6,776.82 per EACH for item 0425-2-93, manholes, j-8, partial, over the 24 months to 28 OCT 2026, across 6 low bids. Half of all 27 bids fell between $5,666.35 and $8,212.50.

Owner
Florida DOT
Item
0425-2-93
Unit
EACH
Latest letting
10 JUN 2026
$6,776.82Low bidder's median, per EACH
$7,000.00Median of all bids, per EACH
6Contracts in the window

By year of letting

Manholes, j-8, partial, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201899$3,230.0044$3,380.97
201955$4,570.0023$4,337.71
202066$5,272.2324$5,699.47
202166$4,458.0025$4,500.00
202255$5,311.8218$4,328.62
202399$6,148.0038$6,000.00
202433$8,373.7516$8,136.88
202533$7,053.647$7,820.00
202633$6,500.0020$6,400.26
Manholes, j-8, partial, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Manholes, j-8, partial, FDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 411$6,148.0064$5,076.50
District 511$4,570.0044$5,080.00
District 79$3,544.4739$5,500.00
District 210$5,270.0031$5,110.00
District 16$4,608.3030$3,970.00
Manholes, j-8, partial, FDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Manholes, j-8, partial, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 112$4,207.20
1 to 212$6,044.00
2 to 312$5,994.99
3 to 1013$4,400.00
Manholes, j-8, partial, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Manholes, j-8, partial
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
10 JUN 2026T5888District 54$8,000.00$6,650.268C.W. ROBERTS CONTRACTING, INC.FDOT
20 MAY 2026T4666District 45$6,500.00$6,810.008OHLA USA INCFDOT
28 JAN 2026T1922District 11$5,660.00$5,678.144SUPERIOR ASPHALT, INC.FDOT
24 SEP 2025T5867District 52$7,053.64$7,436.822CHINCHOR ELECTRIC INC.FDOT
28 MAY 2025T2A20District 21$13,356$13,3561ANDERSON COLUMBIA CO., INC.FDOT
29 JAN 2025T2994District 21$4,050.00$7,282.254COXWELL, J.B. CONTRACTING, INC.FDOT
25 SEP 2024T4714District 41$8,373.75$8,373.755FERREIRA CONSTRUCTION CO., INC.FDOT
31 JUL 2024T7554District 71$8,569.64$9,958.725PREFERRED MATERIALS INC.FDOT
28 FEB 2024T7521District 76$3,500.00$4,895.076WATSON CIVIL CONSTRUCTION, INC.FDOT
06 DEC 2023T1887District 11$5,402.19$8,387.894WRIGHT CONSTRUCTION GROUP, INC.FDOT
25 OCT 2023T4651District 42$19,724$10,7294OHLA USA INCFDOT
25 OCT 2023T7523District 71$6,181.17$7,600.005PREFERRED MATERIALS INC.FDOT
27 SEP 2023T4615District 41$8,400.00$9,500.002CONE & GRAHAM, INC.FDOT
26 APR 2023T2924District 21$3,203.24$5,700.003HUBBARD CONSTRUCTION COMPANYFDOT
26 APR 2023T4613District 44$4,500.00$4,863.708DE MOYA ASPHALT JOINT VENTUREFDOT
Latest FDOT contracts carrying Manholes, j-8, partial

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.