Reinforcing steel- roadway unit price, Florida

Low bidders on FDOT contracts carried a median of $1.75 per LB for item 0415-1-1, reinforcing steel- roadway, over the 24 months to 28 OCT 2026, across 19 low bids. Half of all 84 bids fell between $1.40 and $3.21.

Owner
Florida DOT
Item
0415-1-1
Unit
LB
Latest letting
28 OCT 2026
$1.75Low bidder's median, per LB
$1.79Median of all bids, per LB
18Contracts in the window

By year of letting

Reinforcing steel- roadway, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20182122$1.00128$1.00
20191213$1.6861$1.25
20201314$1.6262$1.62
20211413$1.3559$1.29
202299$3.0033$2.50
20231516$2.1761$2.05
202477$3.2029$2.25
202567$1.6533$1.58
20261111$2.0049$2.00
Reinforcing steel- roadway, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Reinforcing steel- roadway, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 37$2.0027$2.25
District 25$1.6522$1.67
District 73$3.8516$2.74
Reinforcing steel- roadway, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Reinforcing steel- roadway, FDOT: low bidder's median by quantity band
Quantity (LB)Low bidsLow-bid median
69 to 1,2414$3.98
2,713 to 20,6555$3.70
23,566 to 57,2895$1.57
70,138 to 271,9505$1.65
Reinforcing steel- roadway, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Reinforcing steel- roadway
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T3970District 319,200$3.70$2.455RBM CONTRACTING SERVICES, LLCFDOT
30 SEP 2026T2A80District 2100,011$1.39$1.753ANDERSON COLUMBIA CO., INC.FDOT
26 AUG 2026T2A69District 2921$4.75$5.984WATSON CONSTRUCTION COMPANY, LLCFDOT
29 JUL 2026T3920District 320,655$3.90$2.386C.W. ROBERTS CONTRACTING, INC.FDOT
10 JUN 2026T2A50District 257,289$0.54$2.053ANDERSON COLUMBIA CO., INC.FDOT
20 MAY 2026T1933District 171,069$1.75$1.536OHLA USA INCFDOT
20 MAY 2026T3992District 32,713$2.00$2.003ROADS, INC. OF NWFFDOT
20 MAY 2026T7587District 71,241$8.38$2.775HUBBARD CONSTRUCTION COMPANYFDOT
29 APR 2026T7562District 723,566$2.00$2.007WATSON CIVIL CONSTRUCTION, INC.FDOT
25 MAR 2026T3939District 339,687$1.57$2.003RJ GORMAN CONTRACTING LLCFDOT
28 JAN 2026T7580District 711,311$3.85$3.674AJ GENERAL CONSTRUCTION SERVICES, INC.FDOT
03 DEC 2025T3993District 341,675$1.15$1.684ANDERSON COLUMBIA CO., INC.FDOT
24 SEP 2025T2A24District 2271,950$1.65$1.496MASTEC CIVIL LLCFDOT
24 SEP 2025T2A24District 2137,250$1.75$1.496MASTEC CIVIL LLCFDOT
30 APR 2025T3926District 369$1.00$9.364PEAVY & SON CONSTRUCTION CO., INC.FDOT
Latest FDOT contracts carrying Reinforcing steel- roadway

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.