Reinforcing steel- bulkhead unit price, Florida
Low bidders on FDOT contracts carried a median of $2.50 per LB for item 0415-1-8, reinforcing steel- bulkhead, over the 24 months to 28 OCT 2026, across 13 low bids. Half of all 72 bids fell between $1.98 and $2.81.
- Owner
- Florida DOT
- Item
- 0415-1-8
- Unit
- LB
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 8 | 8 | $1.20 | 50 | $1.17 |
| 2019 | 9 | 9 | $1.34 | 43 | $1.30 |
| 2020 | 4 | 4 | $1.02 | 19 | $1.01 |
| 2021 | 6 | 6 | $1.75 | 24 | $1.57 |
| 2022 | 3 | 3 | $2.10 | 19 | $1.86 |
| 2023 | 4 | 4 | $1.91 | 19 | $1.80 |
| 2024 | 2 | 3 | $1.35 | 10 | $1.90 |
| 2025 | 7 | 6 | $2.50 | 33 | $2.30 |
| 2026 | 7 | 7 | $2.50 | 39 | $2.15 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 4 | 4 | $2.30 | 21 | $2.00 |
| District 3 | 3 | $2.50 | 13 | $2.58 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LB) | Low bids | Low-bid median |
|---|---|---|
| 247 to 562 | 3 | $3.50 |
| 2,003 to 2,960 | 3 | $2.50 |
| 3,392 to 16,857 | 3 | $3.00 |
| 21,353 to 59,054 | 4 | $1.85 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T3970 | District 3 | 7,233 | $3.50 | $3.50 | 5 | RBM CONTRACTING SERVICES, LLC | FDOT |
| 20 MAY 2026 | T5882 | District 5 | 31,627 | $1.69 | $2.15 | 10 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 29 APR 2026 | T2809 | District 2 | 370 | $3.50 | $3.50 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 29 APR 2026 | T3919 | District 3 | 2,960 | $2.50 | $2.50 | 4 | F & W CONSTRUCTION COMPANY, INC. | FDOT |
| 29 APR 2026 | T7562 | District 7 | 247 | $4.35 | $2.00 | 7 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 31 MAR 2026 | T3845 | District 3 | 16,857 | $1.90 | $2.72 | 4 | PHOENIX CONSTRUCTION SERVICES, INC. | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 2,003 | $1.50 | $1.82 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 29 OCT 2025 | T1917 | District 1 | 7,001 | n/a | $2.90 | 3 | OHLA USA INC | FDOT |
| 27 AUG 2025 | T4688 | District 4 | 59,054 | $1.85 | $2.16 | 7 | CENTRAL CIVIL CONSTRUCTION CO. | FDOT |
| 11 JUN 2025 | T1904 | District 1 | 3,392 | $3.00 | $3.38 | 2 | RUSSELL ENGINEERING, INC. | FDOT |
| 26 MAR 2025 | T4699 | District 4 | 21,353 | $3.18 | $2.00 | 4 | TIMOTHY ROSE CONTRACTING, INC. | FDOT |
| 26 FEB 2025 | T4691 | District 4 | 23,347 | $1.85 | $1.85 | 5 | MASTEC CIVIL LLC | FDOT |
| 26 FEB 2025 | T4712 | District 4 | 2,907 | $2.75 | $2.75 | 5 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 26 FEB 2025 | T6602 | District 6 | 562 | $2.25 | $2.30 | 7 | HORIZON CONTRACTORS, INC. | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 53,870 | $1.25 | $1.25 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.