Low bidders on FDOT contracts carried a median of $7,733.25 per EACH for item 0685-1-12, uninterruptible power supply, furnish and install, online/double conversion, over the 24 months to 28 OCT 2026, across 13 low bids. Half of all 63 bids fell between $5,878.90 and $10,231.
- Owner
- Florida DOT
- Item
- 0685-1-12
- Unit
- EACH
- Latest letting
- 29 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 4 | 4 | $6,722.02 | 17 | $6,970.00 |
| 2019 | 6 | 6 | $7,450.00 | 21 | $7,400.00 |
| 2020 | 6 | 6 | $6,812.51 | 25 | $6,807.88 |
| 2021 | 6 | 6 | $7,498.51 | 27 | $7,265.00 |
| 2022 | 17 | 18 | $8,962.10 | 56 | $8,600.00 |
| 2023 | 11 | 11 | $7,180.00 | 36 | $5,000.00 |
| 2024 | 6 | 6 | $10,125 | 24 | $11,005 |
| 2025 | 6 | 6 | $8,065.00 | 26 | $9,325.00 |
| 2026 | 6 | 6 | $7,084.77 | 32 | $6,178.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 3 | $11,990 |
| 3 to 4 | 3 | $5,557.60 |
| 4 to 6 | 3 | $7,733.25 |
| 7 to 12 | 4 | $7,843.15 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 JUL 2026 | T5883 | District 5 | 11 | $6,436.30 | $6,300.00 | 9 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 29 JUL 2026 | T5891 | District 5 | 4 | $7,733.25 | $6,009.49 | 4 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 15 JUN 2026 | T5885 | District 5 | 9 | $5,296.00 | $5,710.55 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 10 JUN 2026 | T5884 | District 5 | 12 | $9,327.00 | $7,207.00 | 6 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 25 MAR 2026 | T5876 | District 5 | 3 | $5,557.60 | $5,861.25 | 6 | TIMOTHY ROSE CONTRACTING, INC. | FDOT |
| 28 JAN 2026 | T3988 | District 3 | 5 | $13,278 | $13,278 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 30 JUL 2025 | T5860 | District 5 | 1 | $13,809 | $12,411 | 5 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 30 APR 2025 | T5793 | District 5 | 3 | $11,990 | $11,161 | 7 | P & S PAVING, INC. | FDOT |
| 26 MAR 2025 | T4710 | District 4 | 4 | $7,500.00 | $9,800.00 | 2 | OHLA USA INC | FDOT |
| 29 JAN 2025 | T1907 | District 1 | 3 | $4,463.00 | $6,800.00 | 3 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. | FDOT |
| 29 JAN 2025 | T2994 | District 2 | 1 | $8,630.00 | $8,207.50 | 4 | COXWELL, J.B. CONTRACTING, INC. | FDOT |
| 29 JAN 2025 | T5845 | District 5 | 6 | $2,598.23 | $6,117.64 | 5 | SICE INC | FDOT |
| 30 OCT 2024 | T5834 | District 5 | 7 | $9,250.00 | $8,500.00 | 5 | P & S PAVING, INC. | FDOT |
| 12 JUN 2024 | T3915 | District 3 | 3 | $7,088.93 | $8,300.00 | 3 | GOSALIA CONCRETE CONSTRUCTORS, INC. | FDOT |
| 22 MAY 2024 | T2979 | District 2 | 3 | $12,500 | $12,500 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.