Abandon fill ss unit price, Illinois
Low bidders on IDOT contracts carried a median of $103.29 per LF for item X5509900, abandon fill ss, over the 24 months to 18 SEP 2026, across 13 low bids. Half of all 56 bids fell between $63.75 and $236.96.
- Owner
- Illinois DOT
- Item
- X5509900
- Unit
- LF
- Latest letting
- 19 SEP 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 8 | 8 | $75.63 | 46 | $52.84 |
| 2022 | 10 | 10 | $49.00 | 41 | $50.00 |
| 2023 | 7 | 7 | $49.16 | 20 | $65.00 |
| 2024 | 11 | 11 | $80.00 | 34 | $87.50 |
| 2025 | 12 | 11 | $141.00 | 52 | $142.55 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 6 to 23 | 3 | $141.00 |
| 47 to 55 | 3 | $155.00 |
| 154 to 207 | 3 | $60.00 |
| 223 to 1,267 | 4 | $61.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 19 SEP 2025 | 61K93 | District 01 | 6 | $66.30 | $236.78 | 7 | Lima Contractors | IDOT |
| 19 SEP 2025 | 62B64 | District 01 | 55 | $155.00 | $155.00 | 5 | R. W. Dunteman Company | IDOT |
| 19 SEP 2025 | 62R22 | District 01 | 223 | $40.00 | $144.09 | 3 | D. Construction, Inc. | IDOT |
| 19 SEP 2025 | 62U11 | District 01 | 51 | $274.10 | $200.00 | 3 | Everlast Blacktop Inc. | IDOT |
| 01 AUG 2025 | 61L37 | District 01 | 23 | $141.00 | $165.00 | 9 | Plote Construction, Inc. | IDOT |
| 01 AUG 2025 | 64C24 | District 02 | 348 | $350.00 | $325.00 | 5 | OHLA Central, Inc. | IDOT |
| 13 JUN 2025 | 62X02 | District 01 | 15 | $150.00 | $152.00 | 2 | D. Construction, Inc. | IDOT |
| 13 JUN 2025 | 78943 | District 09 | 154 | $103.29 | $71.65 | 2 | E. T. Simonds Construction Company | IDOT |
| 25 APR 2025 | 62X94 | District 01 | 1,267 | $43.00 | $55.00 | 4 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | IDOT |
| 25 APR 2025 | 85774 | District 02 | 207 | $19.00 | $27.50 | 4 | Valley Construction Co. | IDOT |
| 07 MAR 2025 | 61L05 | District 01 | 47 | $145.00 | $125.00 | 5 | D'Land Construction, LLC | IDOT |
| 17 JAN 2025 | 61K81 | District 01 | 590 | n/a | $25.00 | 3 | Austin Tyler Construction, Inc. | IDOT |
| 08 NOV 2024 | 97846 | District 08 | 199 | $60.00 | $60.00 | 1 | Keller Construction, Inc. | IDOT |
| 20 SEP 2024 | 62R25 | District 01 | 451 | $80.00 | $100.00 | 3 | Walsh Construction Company II, LLC | IDOT |
| 02 AUG 2024 | 62U90 | District 01 | 120 | $35.00 | $35.00 | 5 | K-Five Construction Corporation | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.