Ss cleaned 18 unit price, Illinois
Low bidders on IDOT contracts carried a median of $3.50 per LF for item X5538000, ss cleaned 18, over the 24 months to 18 SEP 2026, across 13 low bids. Half of all 44 bids fell between $2.00 and $14.25.
- Owner
- Illinois DOT
- Item
- X5538000
- Unit
- LF
- Latest letting
- 18 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 8 | 8 | $9.65 | 36 | $9.40 |
| 2022 | 10 | 10 | $9.00 | 32 | $7.50 |
| 2023 | 6 | 6 | $6.60 | 19 | $6.05 |
| 2024 | 3 | 3 | $4.25 | 10 | $6.50 |
| 2025 | 5 | 5 | $3.85 | 13 | $3.50 |
| 2026 | 8 | 8 | $2.50 | 31 | $3.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 35 to 90 | 3 | $10.00 |
| 100 to 200 | 3 | $16.00 |
| 200 to 300 | 3 | $2.00 |
| 408 to 1,191 | 4 | $2.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 SEP 2026 | 62V90 | District 01 | 1,191 | $3.00 | $3.00 | 4 | K-Five Construction Corporation | IDOT |
| 31 JUL 2026 | 62W20 | District 01 | 785 | $7.70 | $6.60 | 6 | D. Construction, Inc. | IDOT |
| 12 JUN 2026 | 80B22 | District 01 | 200 | $2.00 | $2.00 | 4 | K-Five Construction Corporation | IDOT |
| 12 JUN 2026 | 80C48 | District 01 | 90 | $10.00 | $30.00 | 2 | Peter Baker & Son Co. | IDOT |
| 24 APR 2026 | 62K33 | District 01 | 833 | $2.00 | $2.04 | 4 | Plote Construction, Inc. | IDOT |
| 27 FEB 2026 | 61L93 | District 01 | 222 | $2.00 | $2.00 | 4 | K-Five Construction Corporation | IDOT |
| 27 FEB 2026 | 62V09 | District 01 | 79 | $1.00 | $1.00 | 4 | Plote Construction, Inc. | IDOT |
| 16 JAN 2026 | 62F94 | District 01 | 185 | $55.00 | $35.00 | 3 | D. Construction, Inc. | IDOT |
| 01 AUG 2025 | 62N97 | District 01 | 100 | $16.00 | $16.00 | 3 | Everlast Blacktop Inc. | IDOT |
| 01 AUG 2025 | 97863 | District 08 | 35 | $190.00 | $132.50 | 2 | Baxmeyer Construction, Inc. | IDOT |
| 25 APR 2025 | 62J79 | District 01 | 300 | $3.50 | $3.50 | 4 | Plote Construction, Inc. | IDOT |
| 25 APR 2025 | 62R62 | District 01 | 408 | $2.00 | $2.00 | 3 | Areatha Construction Co., Inc. | IDOT |
| 25 APR 2025 | 68A65 | District 04 | 200 | $3.85 | $3.85 | 1 | R. A. Cullinan and Son, a div of UCM, Inc. | IDOT |
| 14 JUN 2024 | 62T51 | District 01 | 359 | $4.25 | $5.62 | 2 | K-Five Construction Corporation | IDOT |
| 14 JUN 2024 | 62U83 | District 01 | 358 | $5.00 | $5.00 | 2 | Dunnet Bay Construction Company | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.