Delineator removal unit price, Illinois

Low bidders on IDOT contracts carried a median of $29.98 per EACH for item X6350120, delineator removal, over the 24 months to 18 SEP 2026, across 30 low bids. Half of all 69 bids fell between $24.00 and $85.00.

Owner
Illinois DOT
Item
X6350120
Unit
EACH
Latest letting
18 SEP 2026
$29.98Low bidder's median, per EACH
$40.00Median of all bids, per EACH
30Contracts in the window

By year of letting

Delineator removal, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202177$12.2311$14.00
20221515$19.8028$28.80
20231010$43.4420$68.34
20241212$42.0023$50.00
20251616$29.2733$31.50
20261111$29.9531$47.64
Delineator removal, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Delineator removal, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 017$35.0022$50.00
District 039$20.0016$20.00
District 046$48.8212$56.55
Delineator removal, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Delineator removal, IDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 107$35.00
10 to 308$27.50
37 to 1007$25.00
102 to 5468$27.48
Delineator removal, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Delineator removal
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202666926District 032$20.00$22.502D. Construction, Inc.IDOT
18 SEP 202697892District 0816$20.00$89.853Plocher Construction Company, Inc.IDOT
12 JUN 202666A91District 03104$29.95$29.951Advanced Asphalt CompanyIDOT
12 JUN 202680B28District 013$35.00$40.005K-Five Construction CorporationIDOT
12 JUN 202680B35District 0145$7.37$91.424K-Five Construction CorporationIDOT
24 APR 202661M11District 012$50.00$712.502Alliance Contractors, Inc.IDOT
24 APR 202680B62District 0137$50.00$50.003Martam Construction IncorporatedIDOT
27 FEB 202666N22District 031$50.00$25.004D. Construction, Inc.IDOT
27 FEB 202668474District 04141$47.64$47.641R. A. Cullinan and Son, a div of UCM, Inc.IDOT
27 FEB 202672C96District 06153$5.50$5.501Illinois Valley Paving, a div of UCM, Inc.IDOT
16 JAN 202662K64District 0168$20.00$100.005F. H. Paschen, S.N. Nielsen & Associates LLCIDOT
07 NOV 202562U41District 01157$30.00$30.001Lorig Construction CompanyIDOT
01 AUG 202568510District 046$28.55$36.772IHC Construction Companies, L.L.C.IDOT
01 AUG 202568B70District 0410$134.56$134.563Otto Baum Company, Inc.IDOT
13 JUN 202564R16District 02100$25.00$25.003Advanced Asphalt CompanyIDOT
Latest IDOT contracts carrying Delineator removal

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy