Fence removal unit price, Illinois

Low bidders on IDOT contracts carried a median of $10.00 per LF for item X6640104, fence removal, over the 24 months to 18 SEP 2026, across 91 low bids. Half of all 321 bids fell between $7.94 and $15.60.

Owner
Illinois DOT
Item
X6640104
Unit
LF
Latest letting
18 SEP 2026
$10.00Low bidder's median, per LF
$10.00Median of all bids, per LF
95Contracts in the window

By year of letting

Fence removal, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20241918$10.8063$12.36
20254138$10.28138$10.00
20263939$10.00131$10.00
Fence removal, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Fence removal, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0146$10.00205$10.00
District 0210$8.3032$8.70
District 066$5.6818$6.05
District 038$11.8817$11.00
District 047$13.0017$17.00
District 094$2.7311$3.30
District 056$19.249$20.00
District 083$10.609$11.15
Fence removal, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Fence removal, IDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
6 to 9222$17.00
100 to 26523$10.60
286 to 1,11523$8.00
1,171 to 37,14423$6.83
Fence removal, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Fence removal
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202661L85District 01150$10.00$10.005ICC Group Inc.IDOT
18 SEP 202668E86District 04265$13.00$14.003Stark Excavating, Inc.IDOT
18 SEP 202697892District 08195$10.00$11.153Plocher Construction Company, Inc.IDOT
31 JUL 202661M13District 01250$8.76$8.766Dunnet Bay Construction CompanyIDOT
31 JUL 202662T84District 0112$20.00$50.003D. Construction, Inc.IDOT
31 JUL 202664V30District 023,021$25.00$16.502Clean Cut Tree Service, Inc.IDOT
31 JUL 202685781District 022,224$5.00$5.254Miller Trucking & Excavating CompanyIDOT
31 JUL 202692621District 061,115$6.11$6.554Illinois Valley Paving, a div of UCM, Inc.IDOT
31 JUL 202693856District 06123$8.50$8.501C-Hill Civil Contractors, Inc.IDOT
12 JUN 202662L30District 0152$11.44$11.026D. Construction, Inc.IDOT
12 JUN 202662R61District 01699$7.29$8.003OHLA Central, Inc.IDOT
12 JUN 202662U72District 011,473$9.07$5.025Martam Construction IncorporatedIDOT
12 JUN 202662V08District 0192$11.44$11.443D. Construction, Inc.IDOT
12 JUN 202664L94District 021,554$10.00$10.484Valley Construction Co.IDOT
12 JUN 202666A91District 03814$5.54$5.541Advanced Asphalt CompanyIDOT
Latest IDOT contracts carrying Fence removal

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way