Fire hydnts relocated unit price, Illinois

Low bidders on IDOT contracts carried a median of $5,753.00 per EACH for item 56400400, fire hydnts relocated, over the 24 months to 18 SEP 2026, across 25 low bids. Half of all 104 bids fell between $5,000.00 and $8,662.50.

Owner
Illinois DOT
Item
56400400
Unit
EACH
Latest letting
31 JUL 2026
$5,753.00Low bidder's median, per EACH
$6,453.01Median of all bids, per EACH
25Contracts in the window

By year of letting

Fire hydnts relocated, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202166$4,018.1439$4,640.75
202266$3,575.0020$6,300.00
202377$5,526.0020$5,513.00
202499$5,000.0040$6,754.00
20251111$5,753.0046$5,570.00
20261111$5,000.0042$7,450.00
Fire hydnts relocated, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Fire hydnts relocated, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0114$5,610.0064$6,900.00
District 025$5,753.0023$5,550.00
District 033$5,000.007$5,632.00
Fire hydnts relocated, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Fire hydnts relocated, IDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 16$7,530.51
1 to 26$4,958.43
2 to 36$9,537.00
3 to 97$5,550.00
Fire hydnts relocated, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Fire hydnts relocated
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
31 JUL 202662W20District 011$3,500.00$7,000.006D. Construction, Inc.IDOT
12 JUN 202662L30District 013$3,500.00$3,640.006D. Construction, Inc.IDOT
12 JUN 202662R61District 012$12,231$10,0003OHLA Central, Inc.IDOT
24 APR 202661L48District 011$4,916.85$5,203.432William Charles Construction Company, LLCIDOT
24 APR 202666M55District 031$5,000.00$5,000.001D. Construction, Inc.IDOT
24 APR 202687899District 034$4,000.00$11,0003Austin Tyler Construction, Inc.IDOT
27 FEB 202662R23District 011$4,000.00$5,000.003D. Construction, Inc. & Kraemer North America, LLC JVIDOT
27 FEB 202685769District 021$9,000.00$8,340.006N-Trak Group LLCIDOT
16 JAN 202661J01District 013$7,450.00$7,450.005R. W. Dunteman CompanyIDOT
16 JAN 202662W47District 013$6,500.00$13,6234D. Construction, Inc.IDOT
16 JAN 202685780District 021$12,000$7,790.043McCarthy Improvement CompanyIDOT
07 NOV 202585785District 023$5,753.00$6,126.506Gensini Excavating, Inc.IDOT
19 SEP 202561L28District 011$6,406.01$7,453.014Martam Construction IncorporatedIDOT
19 SEP 202562R22District 011$5,000.00$7,087.073D. Construction, Inc.IDOT
19 SEP 202597833District 082$15,350$9,740.002Keller Construction, Inc.IDOT
Latest IDOT contracts carrying Fire hydnts relocated

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy