Low bidders on IDOT contracts carried a median of $7,000.00 per EACH for item 56400100, fire hydnts to be mvd, over the 24 months to 18 SEP 2026, across 17 low bids. Half of all 94 bids fell between $6,316.47 and $11,061.
- Owner
- Illinois DOT
- Item
- 56400100
- Unit
- EACH
- Latest letting
- 12 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 5 | 5 | $3,300.00 | 35 | $5,500.00 |
| 2022 | 9 | 9 | $6,000.00 | 45 | $6,000.00 |
| 2023 | 8 | 8 | $6,811.50 | 26 | $7,757.75 |
| 2024 | 9 | 9 | $5,350.00 | 32 | $5,550.00 |
| 2025 | 12 | 12 | $7,000.00 | 66 | $7,519.00 |
| 2026 | 3 | 3 | $7,500.00 | 19 | $7,594.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 4 | $9,375.00 |
| 1 to 2 | 4 | $8,625.00 |
| 2 to 3 | 4 | $7,000.00 |
| 3 to 8 | 5 | $6,500.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 JUN 2026 | 93854 | District 06 | 1 | $5,500.00 | $6,750.00 | 2 | Phoenix Corporation of the Quad Cities | IDOT |
| 24 APR 2026 | 61L84 | District 01 | 1 | $7,500.00 | $7,500.00 | 7 | K-Five Construction Corporation | IDOT |
| 16 JAN 2026 | 61L36 | District 01 | 3 | $8,000.00 | $7,747.00 | 10 | Acura Inc. | IDOT |
| 07 NOV 2025 | 61L43 | District 01 | 1 | $11,250 | $9,750.00 | 7 | K-Five Construction Corporation | IDOT |
| 19 SEP 2025 | 61L35 | District 01 | 6 | $6,500.00 | $6,275.00 | 6 | A Lamp Concrete Contractors, Inc. | IDOT |
| 19 SEP 2025 | 61L70 | District 01 | 1 | $11,250 | $9,750.00 | 10 | Triggi Construction, Inc. | IDOT |
| 19 SEP 2025 | 62B64 | District 01 | 2 | $12,550 | $8,535.00 | 5 | R. W. Dunteman Company | IDOT |
| 01 AUG 2025 | 61L46 | District 01 | 4 | $7,000.00 | $12,467 | 7 | A Lamp Concrete Contractors, Inc. | IDOT |
| 01 AUG 2025 | 61L58 | District 01 | 2 | $5,900.00 | $6,469.00 | 8 | Plote Construction, Inc. | IDOT |
| 13 JUN 2025 | 61L52 | District 01 | 2 | $13,250 | $12,831 | 2 | Alliance Contractors, Inc. | IDOT |
| 25 APR 2025 | 95940 | District 07 | 3 | $6,750.00 | $6,750.00 | 1 | Kinney Contractors, Inc. | IDOT |
| 17 JAN 2025 | 61J25 | District 01 | 2 | $6,000.00 | $4,100.00 | 4 | P. T. Ferro Construction Co. | IDOT |
| 17 JAN 2025 | 61K07 | District 01 | 1 | $7,000.00 | $7,538.00 | 4 | Schroeder Asphalt Services, Inc. | IDOT |
| 17 JAN 2025 | 61K81 | District 01 | 6 | $4,000.00 | $3,810.50 | 4 | Austin Tyler Construction, Inc. | IDOT |
| 17 JAN 2025 | 61K98 | District 01 | 1 | $16,880 | $12,940 | 8 | Triggi Construction, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.